Second soil test after demolition
Page 1 of 1
If so, how much was the variation.
Thanks
We had several engineering changes after our second soil test (in our favour), but they also added in root barrier across the whole front of our slab which cost around $2K. In the end it balanced out that we only paid an extra $100 for site costs in the PCV. We didn't have to pay for this PCV as Henley had to include it to re-engineer the slab, so we took advantage of it and added in several other things including extra powerpoints and evap cooling. So in the end, the PCV cost us about $6K.
It was done after our demo with Henley. The soil is disturbed and there was a house in the way, so to get an idea of what was 'under' the old house and where the new slab was going they did another. There may have been rock etc that they could not possibly know about with the other house in the way. Our soil was quite sandy but with deposits of clay in some sections, and we also had 6 mature trees taken out, so the soil was stirred up a lot!
Our is a demo site and will require a second soil test soon.
Currently have allowance for a P class slab, so we will see what happens after the second soil test. We are taking down 9 big mature trees, so there will be a fair amount of movement in the soil. We are hoping the site can't get much worse than P class!! It's all about the trees for us... hoping they won't find a septic tank buried under there anywhere!
Instead of a post-contract variation, we are waiting on the information prior to finalising the contract ~ everything else is pretty much done + waiting on this. Our builder prefers for the second soil test to be done *prior* to the contract being finalised, so that the contract reflects to the fullest extent the expectation of what site costs are required for the block.
Don't know if that helps ~ good luck + keep us posted.
~ cheers, J
Hi Yellow, we are hanging out for the completion of the demo ~ they have started taking our old house down last week ~ as then we will have a second soil test completed. Site costs can then be finalised.
Currently have allowance for a P class slab, so we will see what happens after the second soil test. We are taking down 9 big mature trees, so there will be a fair amount of movement in the soil. We are hoping the site can't get much worse than P class!! It's all about the trees for us... hoping they won't find a septic tank buried under there anywhere!
Instead of a post-contract variation, we are waiting on the information prior to finalising the contract ~ everything else is pretty much done + waiting on this. Our builder prefers for the second soil test to be done *prior* to the contract being finalised, so that the contract reflects to the fullest extent the expectation of what site costs are required for the block.
Don't know if that helps ~ good luck + keep us posted.
~ cheers, J
Currently have allowance for a P class slab, so we will see what happens after the second soil test. We are taking down 9 big mature trees, so there will be a fair amount of movement in the soil. We are hoping the site can't get much worse than P class!! It's all about the trees for us... hoping they won't find a septic tank buried under there anywhere!
Instead of a post-contract variation, we are waiting on the information prior to finalising the contract ~ everything else is pretty much done + waiting on this. Our builder prefers for the second soil test to be done *prior* to the contract being finalised, so that the contract reflects to the fullest extent the expectation of what site costs are required for the block.
Don't know if that helps ~ good luck + keep us posted.
~ cheers, J
We had singed the contract after the first soil test. We are also in the middle of demolition. We have two trees and our soild was rated P. Will see what happens on the second soil test. We are not using stumps. We do have a fall from front to back. First site Cost $16k
Related
24/07/2023
3
Three options 1 Ask the liquidator 2 Find another PD customer and ask the source of their report 3 Pay for new report
4/02/2024
4
Hi Building Expert, Thank you for the feedback, much appreciated, there is also a code of conduct for building surveyors which they need to follow as well. I am looking…
25/05/2024
4
Its never a good idea to sign a building contract without making sure everything is selected, soil test is done Is are dotted and Ts are crossed and without independent…