Builder used the wrong concrete mix
Page 1 of 1
I'm still waiting for a response but where do I stand on this matter and what would be an appropriate course of action?
Is the 20 mpa likely to be a problem with the same slab design (i.e. pier spacings, 120mm thickness, etc)?
2. what did the engineering specify? If the engineering specifies 25 and you have proof it was poured at 20, the slab needs an engineer to recalc the performance to determine if its still fit for purpose. My guess is it isn't. So even if they give you updated calcs , get a second opinion IMO
HOWEVER if you have no undeniable proof it was a 20mpa mix, you're not going to get very far.
The question should be addressed to the structural engineer that desgned the slab.
Hi all, I'm currently building in Melbourne. We specified a raft slab and the builders plans and engineering specified 25 mpa concrete, however they have poured the slab using 20 mpa concrete (i.e. a weaker mix).
I'm still waiting for a response but where do I stand on this matter and what would be an appropriate course of action?
Is the 20 mpa likely to be a problem with the same slab design (i.e. pier spacings, 120mm thickness, etc)?
I'm still waiting for a response but where do I stand on this matter and what would be an appropriate course of action?
Is the 20 mpa likely to be a problem with the same slab design (i.e. pier spacings, 120mm thickness, etc)?
if that is the case and you have dockets to prove it I suspect you may struggle to get your occupation certificate unless the engineer has signed off on it
There are ways to increase concrete strength from the top as well, such as https://duracore.com.au/product/densi-c ... densifier/
Related
28/07/2023
16
i imagine you also have another contract with an architect? and yeah, whatever other's said about special conditions and appendices
1/11/2023
1
welcome to learning that colours vary in different lighting conditions.