I have received the contract for building a double-storey home with JG King. In my contract, they are showing
Total construction period as 425 days (303 days for construction and 122 days delay).
The penalty of liquidated damage shown as $250/week.
Can someone please advise are these construction period and liquidated damage rates negotiable? Is it because of COVID, Home builder's grant and double storey house causing too many days shown as construction period?
Regards,
Dewan
Construction period and liquidated damage in HIA Contract
Page 1 of 1
Note though that liquidated damages are supposed to be a genuine preestimate of your loss, so you might have to argue your case a bit - eg how much out of pocket will you actually be for the delay?
Related
3/09/2023
1
You talk about deletions, are they variations or PS and PC adjustments? pleas list them
26/02/2024
7
It worked for me in getting all non notified rain days removed from the builders claim, although the LDs was only $50/day
19/11/2023
12
Unless there is something in special conditions the builder does not have to give you timeline. If your demolition contractor has not removed Asbestos and it was found…