Construction period and liquidated damage in HIA Contract

Page 1 of 1
Hi Experts,
I have received the contract for building a double-storey home with JG King. In my contract, they are showing
Total construction period as 425 days (303 days for construction and 122 days delay).
The penalty of liquidated damage shown as $250/week.

Can someone please advise are these construction period and liquidated damage rates negotiable? Is it because of COVID, Home builder's grant and double storey house causing too many days shown as construction period?

Regards,
Dewan
My liquidated damages was $1 per day which i got changed to $500 pw
You can try to negotiate anything you like!
Note though that liquidated damages are supposed to be a genuine preestimate of your loss, so you might have to argue your case a bit - eg how much out of pocket will you actually be for the delay?
Related
3/09/2023
1
Contract Sum Adjustments in HIA contract

Building A New House

You talk about deletions, are they variations or PS and PC adjustments? pleas list them

26/02/2024
7
Water-proofing and liquidated damages

Building A New House

It worked for me in getting all non notified rain days removed from the builders claim, although the LDs was only $50/day

19/11/2023
12
HIA Contract Clause 16.2 Delays to Carrying Out the Works Af

Building A New House

Unless there is something in special conditions the builder does not have to give you timeline. If your demolition contractor has not removed Asbestos and it was found…