emmajane24, there are not many requirement for appearance. There is no restriction on fencing. I remember there should be a tropical tree planted in front yard. Anything else anyone else recall?
I'd like to see such guidelines since they make the look of the estate nicer.
Has anyone visited the estate or got a message from moremoc today?
Moremac representative advised that he could not advise because he was not at the site.
I haven’t heard anything. I’ve got the day off tomorrow so will be driving down in the morning to check things out.
We have just visited the state. It is totally disappointing. They haven't made any progress. It is the same as two weeks ago.
This was the last timeline we received from the contractors, by the way, this is how I found out their name and tracked them down. Was told the owner of the company is interstate and can’t take calls
Please let us know if you get a replay from David cause we too would like to know what they are doing to insure the works get finished.
Just put in a complaint to the contractor head office so I’m really hoping I get a response. I mean how long can you drag out what they have listed in their timeline as 2-3days work
Hi Alyshia, please give us the contact details so that we can write to the head office as well.
The project has fairly well stopped. I have spoke to the director of universal concrete contractors. The asphalt isn’t actually the issue, the soil was tested and still showed too much moisture for asphalt to be laid over so they will be retesting tomorrow or Friday.
Here’s the bad news, the contractors don’t have a sub station to install. Without this nothing gets finished. According to the owner of the company the configuration of sub station our estate requires are in short supply large demand. He has told me the supplier has informed him and his company the earliest they will have a sub station to him will be mid November but most likely late November. This will now push completion back till end of November. Which if it means anything should still allow builds to start January/February.
He is going to try and email me through some further details on the sub station and has promised to keep me informed
Even if they finish it by late Nov, which I am doubtful about. it will take another 4 weeks for title and it means that it will go after Christmas holidays. So maybe in late January the land is getting titled. So ...
Related
15/02/2024
3
Adam Baines Grad Cert Bldg Surv / Grad Dip Bldg Surv / MSAAPA Accredited Building Professional APB20210035 Builders Lic 183023 Pest Control Lic 84868 Ph 0412202336 PO…
9/08/2023
4
Well these guys are not looking good... I sent them a written enquiry last week and they have not yet replied. If they cannot respond to a simple…