Update KDR:
----------------
Planning/Quotes Jan to Jul 2016
---------------------------------
[SPOILER]
12/01/2016 first quotation
16/01/2016 second quotation
12/03/2016 third quotation and floor plan draft
24/04/2016 first draft full drawings
Comment:***** five star service from SJD sales (Leigh)
29/05/2016 colour selection
15/06/2016 fourth quotation
04/07/2016 section29a consent to demolish approved
Comment: was expecting this to delay us but was wrong. (Took 2 days)
06/07/2016 pre-approved loan
09/07/2016 Signed building contract/drawings
20/07/2016 Electricity meter removed
Comment: United Energy were very responsive in getting this done (5days)
21/07/2016 demolition quotes
[/SPOILER]
Demolition/Permits/Plans-Approvals-Aug 2016
----------------------------------------
[SPOILER]
03/08/2016 engaged independent inspector DARBECCA to oversee stages
05/08/2016 asset protection approved
15/08/2016 gas meter removed
Comment:very slow process. (Took 25 days)
16/08/2016 asbestos removal
18/08/2016 cancelled insurance
18/08/2016 started demolishing house
Comment:EXPRESS DEMOLITION-*****Great service took 5 days fully cleared.
22/08/2016 finance approved
22/08/2016 requested underground electricity pit from UE
23/08/2016 land cleared-Waiting for sewer capping
23/08/2016 paid deposit to builder
23/08/2016 confirmed all stages to be overseen by DARBECCA
24/08/2016 received loan contract
26/08/2016 signed loan contract
Comment:whole loan process was a disaster...(took 2.5 months)
26/08/2016 received underground electricity pit quote 3phase($3600). Replied to proceed.
29/08/2016 building permit approved(waiting for copies of stamped plans). Proposed start build date mid Sept
30/08/2016 sewer capped
31/08/2016 received Plans stamped and approved
[/SPOILER]
Pre-Build Sept 2016
---------------------
[SPOILER]
01/09/2016 Electricity pit amount deducted
02/09/2016 Construction loan ready by bank
07/09/2016 site supervisor assigned, works to begin Monday yay!
07/09/2016 requested demolisher temp to be remove to allow allow for builder temp fencing
08/09/2016 demolisher's temp fence removed
09/09/2016 site cut and builder fence up
13/09/2016 bricks delivered (rainy-no activity)
14/09/2016 (rainy-no activity)
15/09/2016 (rainy-no activity)
16/09/2016 (rainy-no activity)
19/09/2016 piers bored and filled
20/09/2016 electricity meter installed
22/09/2016 under slab plumbing
22/09/2016 electricity pit installed
Comment:very slow process took 25 days
26/09/2016 no activity
27/09/2016 no activity
28/09/2016 no activity (steel delivered)
29/09/2016 PRE-pour base steel preparation done
29/09/2016 DARBECCA inspection performed at 3pm (paid invoice)
Comment: 4-Defects reported. However the overall inspection reported as very well presented base. Happy with that
. Waiting for SS to confirm fixes. Confirmed minor defects will be done on the pour day
[/SPOILER]
Build Oct 2016
---------------------
[SPOILER]
03/10/2016 slab poured, yay!
04/10/2016 invoiced, sent bank progress payment claim for base
05/10/2016 some soil was cleared and rubbish-bobcat looks to have been operated on the slab, can see the tracks of dirt(been rainy so may wash off)
06/10/2016 no activity
07/10/2016 no activity
10/10/2016 bank confirmed BASE progress payment processed
11/10/2016 frames started
12/10/2016 frames continued
13/10/2016 more frames continued yay! Can now see the Porch area and what will be the balcony
14/10/2016 first floor chipboard installed
17/10/2016 first floor frames started
18/10/2016 trusses delivered
19/10/2016 more work on first floor frames looks completed
20/10/2016 electricity meter installed
21/10/2016 invoiced for frame, requested bank progress payment
24/10/2016 window frames delivered
25/10/2016 ground level windows installed
26/10/2016 no activity
26/10/2016 DARBECCA inspection done
Comment: Again, a well presented frame reported. Shows quality of their work
27/10/2016 informed SS of defects by report. SS will look at fixing important ones
27/10/2016 tin roof gutters delivered
28/10/2016 gutters started
29/10/2016 gutters finished
31/10/2016 tin roof started and finished
[/SPOILER]
Build Nov 2016
01/11/2016 public holiday
02/11/2016 insulation started
05/11/2016 bricks delivered
08/11/2016 SS walk through frame with fixes.
09/11/2016 brick layer started job
10/11/2016 bricks we're laid, garage wall /some pluming done
11/11/2016 more bricks laid
14/11/2016 more bricks
15/11/2016 bricks/ plumbing
16/11/2016 bricks/plumbing
17/11/2016 bricks/Windows installed (level 1)
11/11/2016 bricks
14/11/2016 To 19/11/2016 bricks
21/11/2016 To 26/11/2016 bricks and garage roof installed