Has anyone had issues with there provisional items being way off the mark ?
I am now starting to really question Clarendon quoting an tendering process.
When we started this process the price difference between the initial quote an tender quote was over $75k. My wife and I were little taken back, it was the explained to us the sales person may not have know other things to take into account when quoting, hence the large price difference. So we did our sums and worked out we can afford the tender quote, and proceeded onto the next step.
We are about to go into construction, and we received a PCV where basically there was a 15k provisional amount for stormwater hydraulics in the tender, now they want an additional 15k on top of the provisional amount
.
I am getting worried about the other provisional items and are we are going to get hit with additional PCV's adding to the other provisional items. Thereby throwing our budget out the window.
Anyone else had this happen to them, if so what can I expect. I dont really want to go back to the bank and change our loan amount.Sounds something