The wrap and bricks should be started next week. We are doing an inspection inside next Tuesday.
Before: After:
Question for the experts. Is this an acceptable patch for framework not meeting the standard (overhang)?
Before: After:
Before: After:
Ask them for computation and how they guarantee there is enough bond between grout and existing concrete
It's in the construction documentation, allowing for overhang "repairs"!
That's right, this help them to avoid going back to engineer
It's in the construction documentation, allowing for overhang "repairs"!
That's right, this help them to avoid going back to engineer
These details come with limitations, generally not applicable to steel columns supporting double storey section, can you show the whole page which may have additional notes?
That particular one only holds up the garage (metal) roof, and the top lintel with rendered brick. The other side has a steel plate bolted to the slab under the overhang, and holds up the wall and facade. The notes say the following:
it holds a double storey section, it is very clear this rectification should never been used, read notes number 6 second bullet point, has this been sent to engineer for approval?
Hi Gary, how is the construction progressing?
Getting there! We had our frame completed two weeks ago, wrap done, sand arrived, ready to start bricks next!
Bricks now in progress!
Great! things are moving. Any commitment from Metricon on the completion date?
Our new SS says he could have it done by Christmas! I told him we want a good job, not a quick job!
It’s looking good. Congratulations
Mine not far to go
How are you coping with Shepparton's covid worries? Is it slowing your build at all?
It's on Instagram, "Doulton.on.Highton"
Related
13/12/2023
0
Hi, First of all, thank you to this community for sharing your thoughts and opinions. We are in early days of our pre-contract stage for Metricon Doulton and we are…
15/06/2023
0
Hey guys building a new place through a volume builder and just wondering if i should complain to the site supervisor as we just had plasterboard installed. Looks like…