We have moved in since June this year, if you have finilazise your contract I would strongly recommend to upgrade the bathrooms floor to compress board. We didn’t know until it’s too late that Metricon only install yellow tounge flooring too all bathrooms.
We are having Hebel floor, so I think upgrading the floor is not required.
If you not going to store or put cupboards in the garage plus your car then you may have reconsider.
With our garage we have a small Volkswagen eso and a Nisan patrol and cupboards (standard one from Bunning) on both side it’s a bit squzzy.
That is very good idea that you have heble flooring ( if we have the second change we would pick heble floor). Best you ask Metricon sale rep to see what are they going to install on the showers (wet areas).
Metricon suggested a 1M extension, which we are going with.
We looked at hebel also, as some others here said it was better for soundproofing and no squeaky floorboards upstairs, but $20K extra was a bit much (we are building the Doulton 50)! May depend on what other changes we make too, whether we keep it or remove it!
Our current garage is a double, being the standard 6M length, and just fits a Prado with towbar, about 0.5M from panel lift door, and 1M from front wall. We have some furniture in there at present, and a fridge and chest freezer (to the front at the left end, if you had them against the wall in front of the car, there would be almost no room to get past)!
Hello Folks, Glad to see a large family of DOULTON houses I am planing to build in the North, have been to SIGNATURE display house in Greenvale and Doulton display in Burwood. I have got few questions and i am positive to get replies as i can see many experts here of Doulton. This is gonna be our first building Project, i am a bit concern cause i do a lot of interstate & overseas travelling nature of my work. I am also on a Budget, by the looks of it this project is looking very straight forward however, i am sure this won't be the case, by the way we are planning for Doulton 46.
1. Base price is $435k, what you think what extra $$ if i upgrade like flooring, carpets, Kitchen,cooling etc.
2. How long the whole process will take from start till completion?
3. How much i should keep extra $$ for front yard+Back yard+ Fencing etc?
4. What kind of surprises i can face?
5. My block size is 600+SQM approx, do you think it is enough for this type of house?
I am thinking of going for MODE facade to save money and spend on other things.
Your suggestions will be much appreciated
1. Base price is $435k, what you think what extra $$ if i upgrade like flooring, carpets, Kitchen,cooling etc.
2. How long the whole process will take from start till completion?
3. How much i should keep extra $$ for front yard+Back yard+ Fencing etc?
4. What kind of surprises i can face?
5. My block size is 600+SQM approx, do you think it is enough for this type of house?
I am thinking of going for MODE facade to save money and spend on other things.
Your suggestions will be much appreciated
Did you end up going ahead with the Mode facade?
Is this built with Heble Power Panel XL for both levels?
How many render quotes and which manufacture?
Related
2/06/2024
2
I'm on that journey. I had to demolish a single story brick veneer on concrete raft slab about 220 sq meters for about $19k. They took forever to get a permit and I…
13/12/2023
0
Hi, First of all, thank you to this community for sharing your thoughts and opinions. We are in early days of our pre-contract stage for Metricon Doulton and we are…