Our first build: "Bridgewater" by Gj's Shoalhaven
Page 55 of 59
Make sure your bank books in the valuer ahead of time and they get the completion certificates asap as they will delay the final payment being made, we are just scraping by as we were never told of this and are just getting it all in on time (within the two week timeframe is scraping) hoping it all comes together
Our bank manager called as she noticed we were nearing our final payment. I promptly emailed the builder to ask for invoices and occupancy cert so I can forward to bank ready for 2.5 weeks time!!! Omg. Is it really only that long?!
We get keys next Friday!!
JB Removals. Jeff and the team are very approachable. They made our move stress free and smooth. I hope yours too!
How was your move? and the neighbuorhood? When we first moved within Sydney area, we chose the local movers of downpipes on, eaves painted, stone benchtops and sink installed.
they have flooring booked for Monday-wednesday next week so one would hope the painter pulls his finger out and finishes it so they can finish fix out before then...
supposedly we have 13 sleeps till handover...i hope it happens!
The *insert expletive* painters didn't turn up for the week they were booked.
Given they are already a week over contract I gave them an extra 2 days only to finish it.
So handover is now the 30th at 8am. The same time the removalists are due to start the uplift.
We've also had to re schedule our furniture delivery.
However I've sent the final invoice off for processing. Phew!
Fixout is now scheduled for early next week and flooring late next week.
Inspection on Tuesday morning which I assume will be our pci. However we won't be able to check powerpoints etc coz it won't be done yet...not sure what to do there
Hey Reg. We will be as of Monday.
Wow! that came quick... our builds are not as fast as it should be after all...lol
It will happen. It will happen.
When is handover for you??
I know right!
It will happen. It will happen.
When is handover for you??
It will happen. It will happen.
When is handover for you??
Tentatively next Friday.. was suppose to happen today but the builder is not happy with a couple of things and would like it to be fixed before I do the inspection...
I can't wait to move in and share pics cb.
Painters weren't at it so much today but we have our garage door and auto opener.
Toilets and towel rails have arrived as has someone's range hood and stove top that is definitely not ours...
Still waiting on the very special people at the kitchen place to fix their simpleton error and replace my cupboard doors. Can you tell I'm losing my patience?
In other news we've booked the removalist and we are talking with a few different concrete dudes to book in our driveway. Then it's Ariel, fencing and screen doors.
?♀️
Might sound like I'm being pedantic but I'm paying a lot of money for this house and I expect the cabinetry to not have holes in it coz they took an easy fix.
9 sleeps till handover and we have lights and fans!
Our bench tops
You can only see a little bit coz the island is covered from the painters.
Can't remember if I've posted a garage door pic or not lol
Mirrors and shower screens booked for this week. Flooring booked end of this week.
Just got to get the flipping painters back to finish their half job.
Charli I can't wait for you to be at this point.
Related
12/02/2024
0
hi guys. Please be nice. First time home builder in Qld. I would like some feedback please on whether I should build my granny flat first before my main house at the…
30/05/2024
13
Soak wells and electrical run in happening this week! Summit has told me they will relocate the laundry plumbing after the walls are completed. I'm actually pretty happy…
21/02/2024
7
Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing…