Haha! It defiantly has made our work load a lot less!
Re: Building in Cranbourne (Simonds Homes) Week 15
Page 6 of 9
And our bricks have been delivered!!
It's all still moving fast; looks like we are ahead of schedule at this stage but it will all depend on the weather of the next few weeks
How long do the bricks normally take??
Its great seeing the colours come together hey ☺
Happy with just a good job
When you say internal work do you mean like plaster ect?
Our mysimonds says this stage ( bricks, wrap, tiles, gutters) will take until the 24th of October at the moment!! Think we are defiantly going to be ahead of time.
It gets more exciting each stage
We have our first inspection this week for the slab,frame, tiles.. Any recommendations of what to look for??
We had a ** peak already and noticed our ceramic disk taps have been put in as mixers & our alfresco door is damaged. We also need to add our noggings.
Anything major things we should look out for
We have another inspection on Thursday to measure the room sizes as we believe at least one is the wrong size.
Last weeks photos:
Aircon and heating ready to go
Bathroom
Starting to get doors
Last little bit of brick to go
Plasterers due Thursday.
Unfortunately I wish it was an optical illusion the rooms actually look bigger then we thought but the tape measure says otherwise
Will find out exactly on Thursday.
It's looking great, hope the rooms are settled without too much fuss.
viewtopic.php?uid=71435&f=31&t=82862&start=40
viewtopic.php?uid=71435&f=31&t=82862&start=40
Thank you. Looking forward to sorting it all out Thursday
The problem wall was being taken down today and moved to where it should be.
Plasterers were there right on 7.30 and had half the house done by 9.15 should be all sorted today
Then replacement door arriving Monday and damaged door being fixed Wednesday.. Then lock up is complete
A few issues with incorrect taps but should be almost sorted now
Photos from today
Feel like we are still moving fast even though we are internal now
Was hoping they would forget to lock a door.
From what we could see the plaster out the front is in, cornices in and painting done.
Loving the size of the garage so glad we extended
Thankfully we have an offical inspection on Monday
I think the painting is complete and cabinets have started
These are the long distance shots we managed to get
Related
24/08/2023
0
Hi Everyone I learned something this week that I thought would be worth sharing. In NSW a lot of developers of subdivisions put covenants on the land which normally…
14/12/2023
14
I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with…
10/03/2024
0
Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs…