Vulcan Ridge at East Leppington by Cornish Group
Page 2 of 3
Happy New Year!
I called Cornish Group to check the status of Registration. They are hoping for end of February.
Cheers.
There's more info on this forum compared to what I can get out of my builder but at least it's something.
Our problem is that our tender was 365days and its dated from March 2016 when we started this process and a possible price increase if it lapses, so many pushbacks with rego dates.
Was really hoping registration would be end of this month.
Did they give a reason for the delay?
Not really sure why its getting delayed. In fact, I visited the site couple of weeks back, looks like everything is done.
I hope its not too long away.
Does anyone know what land stage we are in ?
I guess whole lot will be get registered together. Vulcan Ridge as whole.
I guess whole lot will be get registered together. Vulcan Ridge as whole.
[/quote
Building with Eden brae. I emailed Cornish today, haven't got a reply yet.
I checked with Cornish Group again today. They asked me to call them next Thursday\Friday (9th or 10th Feb) for more updates. They also mentioned that its with Council already.
The lot numbers are marked on the curb so you can easily find your lot.
They have already put some footpath in some of the streets.
So exciting to see ours for the first time...now just the waiting game.
We drove through the other day too cherryripe_
It must be getting closer... they have flattened everything out and it looks like they have put down grass seed (?) and were watering the lots. Most lots look finished except the ones along jamboree.
We drove through the other day too cherryripe_
We drove through the other day too cherryripe_
I drove through yesterday:).. I received email today to touch base with them again on Friday.. seems it's getting closer
I can't wait.
So gate is permanently open now?
I'll have to go for a drive
Vulcan Ridge Works & Registration Activity
08-Feb-2017: Plan Registration
The subdivision certificate package, lodged with Camden Council in January, is in the final stages of checking. This process has taken longer than expected due to the size of the development at 215 lots, however we understand that the release from Council is imminent.
Please check this live update page regularly in the coming days for further news. The next email update will occur when the plan is lodged with the LPI for registration.
I so hope so!!
I can't wait.
So gate is permanently open now?
I'll have to go for a drive
I can't wait.
So gate is permanently open now?
I'll have to go for a drive
I don't know if it's permanently open but it was open on the weekend.
Related
7/09/2023
6
The warning is on the sticker on the door too. Second the aluminium powdercoat
27/09/2023
0
Hi, can anyone recommend a custom home builder who can build in north east area? Looking to build a custom 4-br energy-efficient home with a max budget of 750k. If they…