windows out of plumb by 5mm
Page 1 of 1
we had issue with issue with window out of plumb by 5mm, and would like to get some advises if this considered within building tolerances or builder must rectify this? we had a few windows out of plumb, one of the window is 2.5m wide, and the others are smaller width.
I am building with Rawson homes.
thanks for your help
Have they done frame straightening etc?
luxbuild, we are not nearly PCI stage. we only found out when we had a site visit with site supervisor the other day. I am not sure if they have done their frame straightening or not as there were more than 1 windows were out of plumb, and there are some more windows which are too high for us to reach and we couldn't measure them. we did engage the inspector at pre-lining, but somehow he missed most of the windows.
hi Has the builder shown you proof its in tolerance?
I agree that you easily need 3-4 hours for a PCI even if you've been watching the build closely along the way.
we had issue with issue with window out of plumb by 5mm,
You need to have this thread moved to the Windows & Doors sub forum.
by the way, how do i move the question to the right forum? i can't seem to find way to do that, thanks
Do sashes and panels operate freely?
I've just seen your other posts and see you are past when they would have done frame straightening etc.
Has the builder shown you proof its in tolerance?
I agree that you easily need 3-4 hours for a PCI even if you've been watching the build closely along the way.
Has the builder shown you proof its in tolerance?
I agree that you easily need 3-4 hours for a PCI even if you've been watching the build closely along the way.
yes i am now almost reaching the PCI inspection. we also engaged our own inspector for the frames and pre-lining stage, but somehow, he missed most of the windows.
no, the builder just told us that they won't fix the window 2.5m wide which is the box window as it will be major work, other windows in Ensuites, they just said 5mm wouldn't be even noticeable. So I guess i will wait until we get our own inspector in and ask.
I am planning to walk my PCI first, definitely take 3-4 hours or more as i will be taking my times slowly and testing everything i could.
when should I get my inspector to come in, before my PCI or after? I am thinking for them to come after my PCI, then the builder rectified my list, after that my inspector can come in, but site supervisor said not enough time to handover. what do you think? thanks
by the way, I am still looking for good inspector, can't seem to find yet. we contacted housepect they charged $984, expensive for us, not sure about the quality of their report and how detailed they are.
How do you know they are out of plumb?
Do sashes and panels operate freely?
Do sashes and panels operate freely?
hi ECOECO, we measured them. we did that from the outside and inside window sills. so we measured right and left corners and middle, then we worked out the differences.
at this stage, we don't have a chance to close and open all windows, but we noticed that the track sills for the panels to open and close is pretty dirty. so I think I will have to check them at my PCI walk after they cleaned the windows.
by the way, how do i move the question to the right forum? i can't seem to find way to do that, thanks
You could report your own post and ask for it to be moved but ECOECO, the resident windows expert, has now seen this thread and posted replies. Probably still worthwhile asking for a transfer later to assist others who later search the Windows & Doors sub forum looking for a topic of importance to them. This thread has a good descriptive title.
Related
16/07/2023
4
Thanks mate, this helped a lot. Managed to get it back in.
19/11/2023
12
Unless there is something in special conditions the builder does not have to give you timeline. If your demolition contractor has not removed Asbestos and it was found…
3/12/2023
2
Thanks for the informative response! I'll feed that back to the site supervisor.