Provisional Sums - Refund & Extra Charge

Page 1 of 1
Does original contract provisional sums include builder margin? How does it works out in real situation?

Say Tender Provisional Sum for Kitchen Joinery is set at $5000.

Refund
Say builder actual cost is $3000 (material & labour). To calculate the refund, which way is right?
R = 5000 - (3000 + 3000x10%[margin] = $1700
or R = (4545[taken 10% margin out]-3000)+10% margin on top = $1700
or R = (5000-3000)+ 0%margin on top = $2000

Extra
Say builder actual cost is $6000. To calculate the extra, which way is right?
E = (6000 + 6000*10%[margin]) - 5000 = $1600
or E = (6000 - 4545[taken 10% margin out]) +10% margin on top = $1600
or E = (6000 - 5000) + 10% margin on top = $1100
Whatever maximises the builder's profit.
Related
13/05/2024
1
Builder demanding 15% variation amount as provisional Sum.

Building A New House

Sorry to hear. All the advice you are going to get on this one comes down to what your contract says and what variations are allowed and the mechanism for them. For…

13/07/2023
12
Private inspector charge by builder

Building A New House

If you already have a contract, is the inspection cost stated in there? If not they would be forced to issue you a variation which you could of course object to.