Joined: 08 Jun 2006 Posts: 1402 Location: Lara, Melbourne
Did you get a site survey done before the architect drew up the plans? If so, they should pay for their error, and confirm inw riting that the additional soil will ot cause other issues in and around the block (ie drainage towards the house.
I did get a Land Surveyor to survey the site prior to drawing plans. These were given to the Architect so the error was by him who did not transpose the levels correctly on the side elevations showing less of a slope than there actually was.
Not sure if I can get anyone to pay for the error?
Joined: 20 Oct 2007 Posts: 181 Location: SE Melbourne
We have a hill in the middle of our building envelope which we may have to dispose of - we have been quoted $200 / truckload for disposal but have also been advised that a company may buy the soil which would be cheaper.
HTH
TDD
_________________ Building an architect designed home out of Insulated Concrete Forms on acreage in semi-rural SE Melbourne.
$200 a load sounds about right if you are disposing of it at a council site.
If you can find someone who needs 200m3 of clean fill it should cost you a lot less.
We recently did the cut for our new house. Total excavated was about 90m3 of which 60m3 was taken away. It took them 3 hours from arrival to departure. You shouild be able to hire a large excavator, say 14 ton, plus tip truck and operators for around $250/hr. Time taken will depend on the proximity of the dump site.
I'd suggest you call some earthmoving firms for a qoute. They know where fill is required, and with a copy of the contour plan will work out exactly how much is to be excavated.
Matt, nobody pays for fill. The cost is always borne by the disposer. I have some more to dispose of and was told this in no uncertain terms when I asked him if he would like to come and get it !!!