May 20, 2013 2:56 pmSign In72 members logged in
homeone® - Australia's home building and renovation resource. home building and renovation
Find ProfessionalsPhotosVideosArticlesExpertsForumAdvertise 
Building Forum » Building, Renovation & Maintenance » Building A New House

Advanced Search

Australia's greatest home building and renovation community providing you with access to the popular building forum, planning and budgeting tools, and the premium building directory.
LoginJoinLearn more

View unanswered posts | View active topics


Building Forum » Building, Renovation & Maintenance » Building A New House

Building the Sahara Q1 by Henley- WE HAVE THE KEYS!!!

New Topic Post Reply  Page 1 of 49
 [ 967 posts ]  Go to page 1, 2, 3, 4, 5 ... 49 Next
  Print view Previous topic | Next topic 
Author Message
tengals
 Post subject: Building the Sahara Q1 by Henley- WE HAVE THE KEYS!!!
PostPosted: Apr 05, 2012 1:24 pm 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
Well I thought it was time to finally start our thread and Blog.

We signed off on the tender yesterday and look forward to signing the contracts in a few weeks.

We were originally going to build with Carlisle and after quite a few hicups early on (and a refusal to honour our original $15,000 credit), we gave them ample chance to come back to us with "anything". The refused on all counts. During the whole process with Carlisle we had other builders wanting our business, but one that stood out way above the rest was Henley. They have been fantastic on all accounts so far, so we can only hope that they continue this way.

I shall start the blog and get some pictures up asap, along with our colour selections etc

If anyone else is thinking of building the Saraha Q1 and want to ask any questions to this point, please do, as I have founf this site really helpful in our quest so far.

So any other henley builders out there?


Last edited by tengals on Feb 13, 2013 4:49 pm, edited 38 times in total.

Top
 Profile  
alex29
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 23, 2012 6:18 pm 
Offline
Junior Member
Junior Member

Joined: 23 Apr 2012
Posts: 12
Hi,

We are building Sahara Q2. We signed the contracts on15th April 2012.

We are happy to see somebody building Sahara. ::

Where are you building? We are building in Melton. Howz your experience so far?


Top
 Profile  
pinknoise
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 24, 2012 6:41 am 
Offline
Loyal Member
Loyal Member

Joined: 14 Apr 2012
Posts: 89
we're with henley too!! :) so how did your tender go? i've read some posts where people were quite surprised on how the costs have skyrocketed as soon as they went on their tender. we will be having ours soon so im quite worried.. by the way, did you go for the land and house package as well? thanks.


Top
 Profile  
dan1978
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 24, 2012 11:25 am 
Offline
Senior Member
Senior Member

Joined: 15 Feb 2012
Posts: 119
We are looking at Henley and Carlisle. What was the $15k credit they wouldn't honour?


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 24, 2012 5:11 pm 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
alex29 wrote:
Hi,

We are building Sahara Q2. We signed the contracts on15th April 2012.

We are happy to see somebody building Sahara. ::

Where are you building? We are building in Melton. Howz your experience so far?


congrats on your contract signing....

we were supposed to sign contracts TODAY, but there were far to many errors in the draft tender and the final drawings. I met with them today to iron out things, there were quite alot of mistakes, some of the things I have asked a few times to change and they still have not been done, which is a disappointing, as we are ready to sign NOW.

The only thing I dont like so far about the process is the lack of understanding regarding
electricals and some of the inclusions....

Anyway hope we can get to the bottom of it soon, i will keep you updated.


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 24, 2012 5:12 pm 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
pinknoise wrote:
we're with henley too!! :) so how did your tender go? i've read some posts where people were quite surprised on how the costs have skyrocketed as soon as they went on their tender. we will be having ours soon so im quite worried.. by the way, did you go for the land and house package as well? thanks.



Hi, no we owned our land at sandhurst already.

The tender pricing most things were spot on, we are pretty happy with the costings etc...


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 24, 2012 5:15 pm 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
dan1978 wrote:
We are looking at Henley and Carlisle. What was the $15k credit they wouldn't honour?


Carlisle offered us $15,000 credit if we signed on the spot to lock in a start date, which we did, in the end we were mis-informed that we could change the promo to the new one if we prefered. which we did when it came out in jan. but then, they pulled the pin on the deal, which really P*SSED us off. so then we went back to the original promo, but thru the to'ing and fro'ing they said they could no longer confirm the start date , ie- we wouldnt make it in time, so then they said old promo, no credit....

we lost our initial 1000.00



Edited by Support Team


Top
 Profile  
alex29
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 27, 2012 8:53 pm 
Offline
Junior Member
Junior Member

Joined: 23 Apr 2012
Posts: 12
Edited by Support Team


Top
 Profile  
alex29
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 27, 2012 8:59 pm 
Offline
Junior Member
Junior Member

Joined: 23 Apr 2012
Posts: 12
tengals wrote:
alex29 wrote:
Hi,

We are building Sahara Q2. We signed the contracts on15th April 2012.

We are happy to see somebody building Sahara. ::

Where are you building? We are building in Melton. Howz your experience so far?


congrats on your contract signing....

we were supposed to sign contracts TODAY, but there were far to many errors in the draft tender and the final drawings. I met with them today to iron out things, there were quite alot of mistakes, some of the things I have asked a few times to change and they still have not been done, which is a disappointing, as we are ready to sign NOW.

The only thing I dont like so far about the process is the lack of understanding regarding
electricals and some of the inclusions....

Anyway hope we can get to the bottom of it soon, i will keep you updated.

Hi

Yeah they dont care about the electricals. we did our electricals with our tender presenter. he was a nice guy, very helpful.
Hope they get the drawings right. keep me posted.


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: Apr 27, 2012 10:09 pm 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
yeah ours was Sam, he was great....

hopefully the drawings and updated stuff is correct early next week so we can sign this thing....


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 01, 2012 1:32 pm 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
still no revised plans or contract/tender yet

hopefully today they say


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 02, 2012 8:51 am 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
ok so first hiccups,

the revised drawings came through and although a few things are fixed, they are STILL WRONG...

I cant understand these drafts people, it's not difficult to understand a coloured in elevation drawing,

render here, and face brick there.....

but no....they still cant get it right....

I will keep you updated,

getting a little frustrated as we have now lost another week and a 5 year old kid could work out some of this simple stuff.


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 03, 2012 9:52 am 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
ok, they resent drawings though, got it right this time, just waiting for revised pricing/tender...

looks to be back on track now

fingers crossed.


Top
 Profile  
destiny
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 06, 2012 10:00 pm 
Offline
Loyal Member
Loyal Member

Joined: 06 May 2012
Posts: 67
Hi everyone,

First time on this blog.
We just agreed to build the Sahara Lux Q1 at Berwick Waters
Not signed anything yet, but will pretty soon, in time for the deadline for the FHOG. The sales consultant is a guy who built for my mum-in-law about 15yrs ago and 9yrs ago, so we are in good hands. Fingers crossed. I'll let y'all know as we go along. Happy to have found the right home that resonates with me


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 07, 2012 11:51 am 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
ok, contracts arrived at our house on friday!

they are all correct!

just waiting for developer approval regarding our crossover re-location now....

hopefully these contracts will be signed this week...


Top
 Profile  
destiny
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 07, 2012 3:05 pm 
Offline
Loyal Member
Loyal Member

Joined: 06 May 2012
Posts: 67
Few questions guys regarding the Henley. This is our first build and we are hoping to sign this week. For those of you well ahead in the process:

1. Can you advise what we should look out for?
2. Does anyone know how much extra it will cost to make my Sahara Q1 look exactly like the display? I know it will cost extras. Does anyone know the cost?
3. Henley are claiming they have included $40,000 worth of luxury inclusions in the deal. Does anyone know what these inclusions are that make up the $40,000 figure?
4. I asked my sales consultant (who is a family friend) about the $450 per week Henley will pay for the first 3years of the loan. He said, yes my build is qualified for it. Has anyone else verified this promotion and are definately getting it?


Awaiting your replies with interest.


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 07, 2012 3:55 pm 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
hi there, hope to answer a few of your questions,

1. just the standard with most volume builders, check everything over and over
2. close to 150K extra
3. check the website, it shows exactly what the inclusions are
4. yes we are getting it and it is exactly as described. note not the first 3 years of the loan. its the first 3 years from settlement date


Top
 Profile  
destiny
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 08, 2012 11:26 pm 
Offline
Loyal Member
Loyal Member

Joined: 06 May 2012
Posts: 67
I understand there is the Land contract and the house contract re the package. The land developer will hold 5% of the cost of the land prior to signing contract with builder. Will this 5% deposit be returned at a later stage??


Top
 Profile  
tengals
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 09, 2012 8:53 am 
Offline
Gold Member
Gold Member

Joined: 09 Apr 2008
Posts: 1228
hi there, i have no idea as we owned the land seperate


Top
 Profile  
destiny
 Post subject: Re: Building the Sahara Q1 by Henley - Our Blog
PostPosted: May 11, 2012 3:56 pm 
Offline
Loyal Member
Loyal Member

Joined: 06 May 2012
Posts: 67
The extras are really expensive. I went to the showroom today at Mt Waverley. The best extra are highly priced. I'll strongly advise anyone to be careful about upgrades, particularly on bricks and certain fixtures. Hopefully we will soon tally up the final amount and sign the contract before the FHOG deadline.


Top
 Profile  
Sort by  
New Topic Post Reply  Page 1 of 49
 [ 967 posts ]  Go to page 1, 2, 3, 4, 5 ... 49 Next

Building Forum » Building, Renovation & Maintenance » Building A New House



Who is online

Users browsing this forum: 1sttimebuilding2012, Althom, Chifley42, crr, Dana, Darrenh, Davelle, DazzaB, Google Feedfetcher, housebythewater, itzeddie, JayDee25, jibs, Joh + Lach, Kaylajanexx, Krrkrj, mitchitygrub, MJ Overture, newhomehunter, OurLindrum52, Rangi83, sanmutgi, shireduplex, turtleschell, Vetra43, Viking1945, xxkatxx and 88 guests



Search for:



homeone® - Australia's home building and renovation resource.
home building and renovation directory
Subscribe

May 2013 Specials

2 x Espresso Table Lamps10 days leftBy Go Lights NSW
These stunning Espresso table lamps from Cafe Lighting are perfect for the bedroom or the living room. 2 of these lamps for less than $40...read more
10% off for the whole of MAY11 days leftBy SQUAREpeg - Moving Specialists VIC
Since you have the huge decision of choosing who to move with we feel it will make your life easier if we give you 10%...read more
Free Gift for all Homeone Customers11 days leftBy The Round Bath Company WA
Purchase any of our Spas from our huge range on Ebay this month, mention HOMEONE and receive a free gift with your first purchase. To...read more
Winter Rug Clearance Catalogue 17 days leftBy Harvey Norman The Carpet and Flooring Specialists ACT
Save, save, save with modern rugs, traditional rugs, shaggy rugs, wool rugs acrylic rugs and polypropylene rugs! There are many colours and designs to choose...read more
10% off 24 days leftBy PR Painting QLD
Receive up to 105 off your next Brisbane painting quote when you mention this advert...read more

Articles

Read Article: Solar Energy FAQ by Go Lights NSWSolar Energy FAQ
Complete and comprehensive Solar Energy and lighting FAQ
Read Article: Outdoor Lighting Glossary by Go Lights NSWOutdoor Lighting Glossary
A description of the popular types of outdoor lighting
Read Article: LEDs - what you didnLEDs - what you didn't know!
You know how hot incandescent bulbs become. That's because they convert…
Read Article: Is your home Conducive to Termites? What to look for.. by Victorian House Inspections VICIs your home Conducive to Termites? What to look for..
Termites can cost you thousands of dollars in repairs and heartache.…
Read Article: AustraliaAustralia's Only Custom Hydrotherapy Spabath Systems
Roundbathcompany is proud to offer a Total product range of hydrotherapy…

Videos

Watch Video: The Marrakech by Dale Alcock Homes WAThe Marrakech
Built with relaxation and flexibility in mind, the Marrakech means you'll…
Watch Video: SlimWall Designer Fences Installation Video by SlimWall Designer Fences VICSlimWall Designer Fences Installation Video
SlimWall Designer Fences are the popular panel fencing innovation that combines…
Watch Video: Modular Wall Systems Factory Acoustic test by Modular Wall Systems VICModular Wall Systems Factory Acoustic test
See the acoustic results achieved from one of our BarrierWalls installed…
homeone® - Australia's home building and renovation resource.  home building and renovation forum
Jump to: 


All posts made to these forums express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
Forum FAQ | Members | Forum Terms of Use | Site Terms of Use | Privacy

homeone.com.au logos, designs, layout, page headers and colour scheme are ® Copyright Homeone Australia & New Zealand 2001-2013 (v3.0)
homeone® is a registered trademark. All rights reserved. ABN 46 625 367 703.