Building Forum » Building, Renovation & Maintenance » Building A New House

Payments - practical completion

New Topic Post Reply  Page 1 of 1
 [ 7 posts ] 
  Print view Previous topic | Next topic 
Author Message
jasmin3
 Post subject: Payments - practical completion
PostPosted: Nov 27, 2011 3:56 pm 
Offline
Junior Member
Junior Member

Joined: 12 Feb 2011
Posts: 43
Hi
I have my practical completion inspection booked this week, and just after some advice re payments.

My understanding is that after this inspection I will be issued an invoice for the final payment, I can then arrange payment during the ten day period that the builder has to fix any final defects.

Is it standard practice to arrange this payment, knowing that there are still a few things to be fixed? Or would you wait until the house is 100% complete before submitting your payment approval to the bank. That seems to run the risk of delaying handover, given that the bank will take a week or so to approve and transfer the payment.

Any advice appreciated, I don't want to delay it, but also don't want to have made final payment, only to find that the builder hasn't finished everything as agreed.

Thanks


Top
 Profile  
Venturai
 Post subject: Re: Payments - practical completion
PostPosted: Nov 27, 2011 4:19 pm 
Offline
Senior Member
Senior Member

Joined: 25 Sep 2011
Posts: 133
This is something I'm concerned about also. We're not at PCI stage yet, but we'll be there in about a month.

The concern, of course, is that once people have your money, they're always a lot less motivated to get the work done. I'd be interested to hear from others who have already been through this stage, and how they handled it. I wouldn't want to delay handover either, but so many people stop caring once they've got your money.

_________________
-
My build thread.. sort of: http://forum.homeone.com.au/viewtopic.php?f=31&t=51388
-


Top
 Profile  
b0son
 Post subject: Re: Payments - practical completion
PostPosted: Nov 27, 2011 5:25 pm 
Offline
Bronze Member
Bronze Member

Joined: 04 Jan 2011
Posts: 194
they'll probably try and push as much as possible to be fixed post-handover during the 3mth warranty.

anyone know legally what they can and cant force us to wait for to be fixed?


Top
 Profile  
joannapaulp
 Post subject: Re: Payments - practical completion
PostPosted: Nov 28, 2011 8:14 am 
Offline
Gold Member
Gold Member

Joined: 03 Dec 2009
Posts: 590
Location: Georges Fair, Moorebank
Submit the paperwork to the bank, but have the payment in the form of a bank cheque, that you give to the builder at handover when you get the keys


Top
 Profile  
Mclaren
 Post subject: Re: Payments - practical completion
PostPosted: Nov 28, 2011 10:57 am 
Offline
Gold Member
Gold Member
User avatar

Joined: 15 Sep 2010
Posts: 5636
Location: Adelaide
joannapaulp wrote:
Submit the paperwork to the bank, but have the payment in the form of a bank cheque, that you give to the builder at handover when you get the keys


Good advice .. we did that but we still came unstuck as we didn't see all the defects until we were living in the house and started cleaning things - there really is too much to check at handover. A lot of things (almost all) were put onto the 3 month maintenance list - even the jobs that were going to be done ASAP didn't happen - took 7 weeks for the tiler to come and this week the gutters will be fixed (3 months since handover) and then everything else will be fixed apparently on 15th December - seems an awful lot to be done in one day in my mind. Having an inspector at PCI is a must!

_________________
For info on our build: viewtopic.php?f=31&t=43093
Built the McLaren by Dechellis - slab down 22 Feb - handover 30 Aug 2011 - and gardens finished 9 Dec 2012!!


Top
 Profile  
joannapaulp
 Post subject: Re: Payments - practical completion
PostPosted: Nov 28, 2011 11:01 am 
Offline
Gold Member
Gold Member

Joined: 03 Dec 2009
Posts: 590
Location: Georges Fair, Moorebank
Mclaren wrote:
joannapaulp wrote:
Submit the paperwork to the bank, but have the payment in the form of a bank cheque, that you give to the builder at handover when you get the keys


Good advice .. we did that but we still came unstuck as we didn't see all the defects until we were living in the house and started cleaning things - there really is too much to check at handover. A lot of things (almost all) were put onto the 3 month maintenance list - even the jobs that were going to be done ASAP didn't happen - took 7 weeks for the tiler to come and this week the gutters will be fixed (3 months since handover) and then everything else will be fixed apparently on 15th December - seems an awful lot to be done in one day in my mind. Having an inspector at PCI is a must!


That is very true - we moved in end of September 2010, had our 3 month inspection March 2011, and all our maintenance items were finally finished in October 2011 (we also picked up a bunch of stuff whilst living there, and also added things that our SS refused to put on the PCI list - as they were "standard" - but have since been fixed)


Top
 Profile  
jasmin3
 Post subject: Re: Payments - practical completion
PostPosted: Nov 28, 2011 9:23 pm 
Offline
Junior Member
Junior Member

Joined: 12 Feb 2011
Posts: 43
joannapaulp wrote:
Submit the paperwork to the bank, but have the payment in the form of a bank cheque, that you give to the builder at handover when you get the keys


Very good advice! I will check with the bank if this is doable. Sounds like a good solution.


Top
 Profile  
Sort by  
New Topic Post Reply  Page 1 of 1
 [ 7 posts ] 

Building Forum » Building, Renovation & Maintenance » Building A New House



Who is online

Users browsing this forum: asj25, Bailey7278, BrianJulie-Ann, donna61, ellev, fmac, Google Feedfetcher, Gristy, janicec, kasyd, Lurgen, Serialbuilder, WildwoodDream and 61 guests



Search for:



Subscribe

May 2013 Specials

Mammoth May Markdowns - 3 Days Only!Ends todayBy Harvey Norman The Carpet and Flooring Specialists NSW
Solution Dyed Classic Carpet for $14.95 sqm and many more mammoth flooring markdowns in store. Don’t Miss Out! ...read more
2 x Espresso Table Lamps5 days leftBy Go Lights NSW
These stunning Espresso table lamps from Cafe Lighting are perfect for the bedroom or the living room. 2 of these lamps for less than $40...read more
10% off for the whole of MAY6 days leftBy SQUAREpeg - Moving Specialists VIC
Since you have the huge decision of choosing who to move with we feel it will make your life easier if we give you 10%...read more
Free Gift for all Homeone Customers6 days leftBy The Round Bath Company WA
Purchase any of our Spas from our huge range on Ebay this month, mention HOMEONE and receive a free gift with your first purchase. To...read more
10% off 19 days leftBy PR Painting QLD
Receive up to 105 off your next Brisbane painting quote when you mention this advert...read more

Articles

Read Article: Interior Design Gets Set for Winter by Dale Alcock Homes WAInterior Design Gets Set for Winter
As the winter chill sets in, we thought now would be…
Read Article: FAQFAQ's - Onlinecarpet.com.au
Does OnlineCarpet install? Yes, OnlineCarpet will install your carpet. We are a…
Read Article: Modular Wall Systems wins Industrial Product of the year and Steel Innovation of the year Awards by Modular Wall Systems VICModular Wall Systems wins Industrial Product of the year and Steel Innovation of the year Awards
The industry leading supplier of stylish, cost-effective acoustic & boundary walls…
Read Article: Solar Energy FAQ by Go Lights NSWSolar Energy FAQ
Complete and comprehensive Solar Energy and lighting FAQ
Read Article: Outdoor Lighting Glossary by Go Lights NSWOutdoor Lighting Glossary
A description of the popular types of outdoor lighting

Videos

Watch Video: The Archipelago II by Dale Alcock Homes WAThe Archipelago II
The sequel of our most popular home design, the Archipelago. For…
Watch Video: Timber Pest Inspections by Resicert Property Inspections WATimber Pest Inspections
Resicert Timber Pest Inspections - Brilliant Inspections, Best Reports, Fast!
Watch Video: The Marrakech by Dale Alcock Homes WAThe Marrakech
Built with relaxation and flexibility in mind, the Marrakech means you'll…
homeone® - Australia's home building and renovation resource.  home building and renovation forum
Jump to: 


All posts made to these forums express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
Forum FAQ | Members | Forum Terms of Use | Site Terms of Use | Privacy

homeone.com.au logos, designs, layout, page headers and colour scheme are ® Copyright Homeone Australia & New Zealand 2001-2013 (v3.0)
homeone® is a registered trademark. All rights reserved. ABN 46 625 367 703.