Post subject: Building a double storey house @ Roof Stage
Posted: Jun 30, 2011 3:35 pm
Junior Member
Joined: 28 Mar 2011 Posts: 25
I am building a double storey house and the builders have almost finished the brickwork.
How long does it take from this point to put the roof on?
Does anyone have a a time scale of how long to the roof come on?
Thank you Ritk
Site works started
File sent to Site Supervisor Monday 13/3/2011 Wednesday 16/3/2011 – Compressed/Levelled Land Air Con Pre Start Tuesday 22/3/2011 Plumbing and foundation started on Tuesday 22/3/2011 and Wednesday 23/3/2011 Slab down on Thursday 24/3/2011 Brickwork starts for downstairs 8/4/2011 2nd Slab in 19/5/2011 Brickwork starts for upstairs 21/6/2011
Post subject: Re: Building a double storey house @ Roof Stage
Posted: Jul 01, 2011 9:14 am
Bronze Member
Joined: 23 Dec 2010 Posts: 150
ours was done before brickwork.strange way to do it though as they hung scaffold up around the gutter line for the roofer then took that down and put proper scaffold up for the bricky.
Post subject: Re: Building a double storey house @ Roof Stage
Posted: Jul 01, 2011 12:58 pm
Bronze Member
Joined: 19 Jul 2010 Posts: 195
Our roof went on first as well. Apparently this is called a reverse build. They did it because the bricky wasn't available. I'd say your roof will go on as soon as the tradie is available.