Browse Forums Building A New House Re: Sezza's Build SOR Perth. waiting.. waiting... 341Feb 18, 2011 5:49 pm Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in Re: Sezza's Build SOR Perth. waiting.. waiting... 342Feb 18, 2011 7:52 pm Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Sezza's Build SOR Perth. waiting.. waiting... 343Feb 19, 2011 2:41 am SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Build 344Feb 21, 2011 11:15 pm SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build 345Feb 22, 2011 11:31 am my new build thread- Ben Trager https://forum.homeone.com.au/viewtopic.php?f=31&t=89826 my switch build thread (2011) https://forum.homeone.com.au/viewtopic.php?f=31&t=36569 Re: Sezza's Perth Build 346Feb 22, 2011 12:57 pm contract 10/11 prestart 04/10 slab 06/10 bricks 07/10 roof 09/10 plaster 10/10 Ceiling 10/10 LOCKUP 10/10 tiling wet areas 11/10 garage floor 11/10 PCI 12.01.11 handover 11.02.11 https://forum.homeone.com.au/viewtopic.php?f=31&t=39361&hilit=malvern+springs We are in !!! Re: Sezza's Perth Build 347Feb 22, 2011 3:51 pm Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Sezza's Perth Build 348Feb 22, 2011 3:53 pm contract 10/11 prestart 04/10 slab 06/10 bricks 07/10 roof 09/10 plaster 10/10 Ceiling 10/10 LOCKUP 10/10 tiling wet areas 11/10 garage floor 11/10 PCI 12.01.11 handover 11.02.11 https://forum.homeone.com.au/viewtopic.php?f=31&t=39361&hilit=malvern+springs We are in !!! Re: Sezza's Perth Build 349Feb 22, 2011 8:26 pm SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build 350Feb 22, 2011 8:30 pm contract 10/11 prestart 04/10 slab 06/10 bricks 07/10 roof 09/10 plaster 10/10 Ceiling 10/10 LOCKUP 10/10 tiling wet areas 11/10 garage floor 11/10 PCI 12.01.11 handover 11.02.11 https://forum.homeone.com.au/viewtopic.php?f=31&t=39361&hilit=malvern+springs We are in !!! Re: Sezza's Build SOR Perth. tiling completed. 351Feb 22, 2011 11:09 pm SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. what do you think??? 352Feb 23, 2011 9:34 am my new build thread- Ben Trager https://forum.homeone.com.au/viewtopic.php?f=31&t=89826 my switch build thread (2011) https://forum.homeone.com.au/viewtopic.php?f=31&t=36569 Re: Sezza's Perth Build.. what do you think??? 353Feb 23, 2011 10:24 am SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. 354Feb 24, 2011 9:42 am SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Build SOR Perth. tiling completed. 355Feb 24, 2011 3:01 pm Building with Life$tyle Homes in Perth SOR Key Dates on First Page of my Thread viewtopic.php?f=31&t=38761 Re: Sezza's Perth Build.. 356Feb 24, 2011 6:00 pm SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. inspection before real PCI today!! 357Feb 25, 2011 12:39 pm Nice clean site As to your tapware I think it will look more interesting if they will go on the site but closer to the wall - like 45 degrees from wall - if you know what I mean contract 10/11 prestart 04/10 slab 06/10 bricks 07/10 roof 09/10 plaster 10/10 Ceiling 10/10 LOCKUP 10/10 tiling wet areas 11/10 garage floor 11/10 PCI 12.01.11 handover 11.02.11 https://forum.homeone.com.au/viewtopic.php?f=31&t=39361&hilit=malvern+springs We are in !!! Re: Sezza's Perth Build.. inspection before real PCI today!! 358Feb 25, 2011 8:33 pm the taps are going to be positioned at the side of the sink but towards the back. is this the same as what you mean agabob??? SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. inspection before real PCI today!! 359Feb 25, 2011 8:43 pm ok... "dear house build diary!!!" today we had a walk through of the house. I guess you could call it the PCI before PCI!!! not alot to worry about that we noticed.... only things that we picked up were: 1 of the linean doors on the inside wasnt painted. on the driveway and at the path near the front door our darker boarder pavers, 1 of them is chipped and another has a defect in it. like a marble effect with limestone!!! there was a hole in one of the bedroom walls, but ths has already been patched up ceilings where they were cracked have also been fixed up. hmmmmmmm. thats all i can really think of at the moment. lights work, taps work, loos flush, garage door works. what else should i look out for?!?!?!?! SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. inspection before real PCI today!! 360Feb 26, 2011 1:48 am Sounds like it's all ready to go then sezza. That is quite 'generous' of your builder to have a pre-PCI inspection! Makes sense though. Take a look here for some good PCI checklists: http://www.anewhouse.com.au/?page_id=235 Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing… 7 19530 1 5012 1 2841 |