09/05/17- Prestart.
23/05/17- Final Docs received.
24/05/17- Final Docs signed and returned. Scheduling commenced.
09/06/17- Developer Approvals received.
26/06/17- Council Building Permit received.
Been two weeks since all approvals were received but we still wait for the admin process to be completed (apparently will be early next week). After that they will give us a start date (approximately 1-2 weeks after admin process is completed, dependent on weather).
As I said... a very long and drawn out process.
I am a little jaded by the ludicrously long process but am hoping my enthusiasm for the build will be sparked again once they finally start moving some dirt around.
Sorry to be the bringer of frustrating news but I wish I'd known how long it was going to take. Maybe I would have been a little more patient if I'd been given more realistic timelines.
That sounds very frustrating, sorry to hear that!
I'm sure your enthusiasm will be peaked once again once you see things start happening though. Fingers crossed it happens for you soon and the bad weather is out of the way by then!!