Browse Forums Building A New House Re: Our Fowler Homes Paris 34 - Jordan Springs 137May 17, 2017 7:46 pm We hit the 12 month mark of build contract start date on the 3rd of May- bit depressing really. Haven't posted anything for a while re any updates, not a great deal happened until last week. Finally waterproofing was completed. Tiles were delivered- and what a debacle that was it ended up with my husband and I having to physically move 4 pallets into the garage off our neighbours driveway as Abruzzo could not get access to the garage due to the site being an absolute rubbish heap. Tony from Abruzzo was amazing and instead of refusing to deliver, worked around us to get them off the truck rather than going back to the warehouse and delaying things further. Thank god I was driving past the house at the right time!! Tiles started this week and will take about two weeks to complete. All the gyprock repairs, sanding and incomplete work will be completed this week too. Our new site supervisor is really good. I have wish we had him from the start- we would have been in months ago I'm sure of it. Re: Our Fowler Homes Paris 34 - Jordan Springs 138May 18, 2017 6:47 am Fowler Homes Hemisphere design is being built in oran park. It was supposed to open for display in February. Its mid may now and they still could not finish their own display home! Re: Our Fowler Homes Paris 34 - Jordan Springs 139May 18, 2017 8:11 am It has been slow for us too with only a bit of work here and there over the last few weeks. I reckon I'm heading for a 15-16 month build I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 109628 Anyone built with Fowler Homes? Feedback? Especially any things concerning or negatives? Have heard some horror… 0 9613 of course there are legal avenues. You've already mentioned it. Sue them. I find it odd that lawyers wouldnt be willing to take on the case, given CCT evidence and… 1 24556 |