I have been reading few posts and learnt a lot, so I thought I would start my own too.
We are doing a knock down rebuild and hoping for a site start in a couple of weeks.
Here is a bit of a timeline so far
21/9/14 Paid 1st deposit
19/11/14 Signed quote. MainVue will now go ahead with soil & site survey
27/11/14 Colour appointment
14/01/15 Tender appointment
16/02/15 Dispo lodged with council for reduced setback
18/03/15 Moved into rental
23/3/15 Applied for gas & electricity to be abolished
08/04/15 Gas abolishment done
08/04/15 Dispo rejected by council.
15/04/15 Found electricity had also been abolished
28/04/15 Received contracts
01/05/15 Temp fence installed in prep for demo
04/05/15 Contracts signed
04/05/15 Demo commenced
06/05/15 Demo finished. (Not a particular good job mind you)
18/05/15 Demo co. Finally came aback to do site scrape and clean
21/05/15 2nd survey done
28/05/15 2nd soil test
09/06/15 Pool commenced. Dug hole, delivered pool and put in place
10/06/15 Pool filled and set.
11/06/15 Pool finished until after handover. Void cover installed
23/06/15 Building permit approved.
10/07/15 Toilet delivered, site scrape & level. House pegged out
13/07/15 Piers done
16/07/15 Electric cables laid and meter box installed
21/07/15 Plumbing rough in done
24/07/15 Termite caps done
27/07/15 Waffle pods laid out, boxed up ready for concrete
28/07/15 Slab poured
05/08/15 Frame started
26/08/15 Gutters & facia installed
31/08/15 Roof started
01/09/15 roof finished
02/09/15 Heating & air con ducts installed
03/09/15 plumbers rough in internal pipes
04/09/15 goop guy
09/09/15 Blue wrap done on frame
10/09/15 Plaster delivered
11/09/15 Bricks delivered
14/09/15 Meeting with SS to go through inspection report
15/09/15 bath hobs installed and walls straighten in prep for plaster
17/09/15 Sparky on site to start on rough in of wiring. Garage roof trusses installed. Bricky turned up to prep
18/09/15 Bricky started laying bricks
22/09/15 Insulation done. Gutter & facia on garage installed
23/09/15 independent inspection done for pre plaster
28/09/15 Garage roof installed
05/10/15 Scaffolding erected around outside to brick upstairs. Meeting with SS
14/10/15 Plaster hung
16/10/15 Bricks all finished
23/10/15 bricks upper level acid washed
26/10/15 Plaster sanded
28/10/15 Eve's installed
30/10/15 Stairs installed
04/11/15 kitchen cabinets installed, bathroom cabinet delivered. Bathrooms waterproofed.
05/11/15 All cabinetry installed.
06/11/15 skirting and arc's installed and doors hung
09/11/15 Tiles delivered
16/11/15 foam board installed on facade and tiler started
25/11/15 facade base coat render done and painter started prep inside
26/11/15 painting