Browse Forums Building A New House Re: Masterton Homes - The next thread 4.0 3082Jan 13, 2015 12:00 pm 2013 1st tender 24/10 Dep. 18/11 2014 5% 25/02 CDC approval 5/5 Demo 26/5 Pool 3/7 Valid'n 10/7 Slab 11/8 Frame 19/9 Bricks 23/10 2015 Roof 3/12 Lock up 11/2 PCI 31/3 Final insp. & keys 30/4 Re: Masterton Homes - The next thread 4.0 3084Jan 13, 2015 12:57 pm Masterton Overture 17/12/14 - Handover ...... we got the keys !! blog - http://www.mcnamaraadventure.blogspot.com Re: Masterton Homes - The next thread 4.0 3086Jan 13, 2015 8:37 pm MGardz Ah I see. Its weird they separate it! We shall be prepared then Thank you...btw...where is the best place recommended to put these cat 6 things in? I was thinking the main place where hubby will have his game thingys Not an expert on networking. Standard they offer is cat5e which is pretty good - we upgraded to cat6 because it wasn't that much more and it future proofs us. We put a data point in where we think we are having tvs / computers, also wherever your modem / router will be. We'll have a switch in the home hub. Hopefully if your hubby is into gaming, he'll know where they should be. Masterton - Jamison Validation 10/03/2015 Slab 18/04/2015 Frames 30/05/2015 Re: Masterton Homes - The next thread 4.0 3087Jan 14, 2015 9:34 am Thank you Edmondss. He's not a massive gamer so i think we will keep it pretty simple and just enough to future proof. Currently stressing about the appointments! Fingers crossed. Re: Masterton Homes - The next thread 4.0 3088Jan 14, 2015 11:27 am Our block was pegged just before Masterton went on there break, so I am eagerly awaiting there return. Does anyone have a timeframe of when they will start building once the block has been pegged? Re: Masterton Homes - The next thread 4.0 3089Jan 14, 2015 2:03 pm Happy new year everyone! I drove past our site on Monday as I headed off with the kids to the Hunter Valley, and our SS is as good as his word, brickies back on site already....phew! Looking forward to finishing brickwork and seeing the roof go on over the next few weeks....! Re: Masterton Homes - The next thread 4.0 3090Jan 14, 2015 5:22 pm shiraz1 Our block was pegged just before Masterton went on there break, so I am eagerly awaiting there return. Does anyone have a timeframe of when they will start building once the block has been pegged? We were pegged on 8th Oct and excavation started on 14th Nov. Patience is definitely a virtue when it comes to building with Masterton!! Having said that there was work going on at our site today which was an unexpected surprise. It was also a shock to see a 4.5 ton excavator on the slab digging trenches for the plumbing Re: Masterton Homes - The next thread 4.0 3091Jan 14, 2015 7:39 pm Happy New Year! After much searching and many trips out to every Homeworld we could find, we have narrowed our choice down to the Villina Lane or The Braedise 33 from Firstyle http://firstyle.com.au/houses/Braeside33-rear.html We've bitten the bullet and Firstyle are writing us up a tender & we are off to Warrick Farm on the weekend to get a tender organised on the Villina. It was another episode in our education on builders when talking to Firstyle, even though they appeared more forthcomming on prices there were some Masterton inclusions we had to specifically ask for - like Granitguard termite treatment, treated timbers and R3.5 insulation bats (Firstyle standard is R1.5). So now we've been careful to include everything in both tenders so that we can get a real comparison between them. We've even ordered a skip for next weekend to start our pre-move out clearance of the detrituce - I think we're one the Woohoo side of the rollercoaster ride at the moment. On another note, there's no gas pipeline in our street (or suburb for that matter) and I don't want the hastle of ordering in LPG bottles every few months, so solar panels & all electric cooking/hot water is looking good. I've even found the gadget I need to divert unused solar power into the hot water system: http://www.australianwindandsolar.com/immersun-products Now I've just got to explain it to M and Firstyle so they can get us the right Basix score. The adventure continues Villina Lane 11/14 $3900 08/15 Contract 11/15 DA Approval 02/16 Demolition 03/16 Peg out 06/16 Slab 06/16 Ground floor frame 07/16 1st floor frame & windows 09-12/16 Bricks blog Re: Masterton Homes - The next thread 4.0 3093Jan 15, 2015 8:26 am Hi All, Firstly i have been reading this forum now for about 2 weeks, and so far have found it invaluable. I am just starting the process, and considering knock down rebuild to a duplex. I think most of this information can still help me, but i was wondering if anyone has built a duplex with Masterton Homes before? Thanks, Muzza Re: Masterton Homes - The next thread 4.0 3094Jan 15, 2015 10:51 am Hi All, We are about to start building with Masterton in Elizabeth Hills (modified Overtue Elite). Our block was pegged and fenced before the christmas break and we were told today that we are now in construction and they have 20 days to commence. Do they generally wait until the 19th day to commence or do they get straight into it? Re: Masterton Homes - The next thread 4.0 3095Jan 15, 2015 12:29 pm Welcome Muzza, this forum truly is helpful with all of the information you will find. I haven't come across any one on here building a duplex yet! Welcome elizabethHills, it all really depends. Some people are lucky to have constrution start straight away, others are not we didnt get a fence or portaloo until the very very last days of the 20 day countdown, and then we had our site cut and fill a few days after the 20 days. We had our slab poured just before christmas break and frames are due to be delivered on Monday! Concerto Elite Re: Masterton Homes - The next thread 4.0 3096Jan 15, 2015 2:46 pm Well, just had a call from our SS to say that he was on our block, and someone has ripped off panels from the back fence and stolen tools off the site over christmas - really odd stuff like specialised brickie tools for scraping mortar etc. I think he thought we would be upset about having to fix the fence, but we are going to replace it when building is finished, so he's just going to put temp fencing across it in the meantime. Seriously, there was literally nothing to steal on site over Christmas...at least it wasn't just vandalism I guess.. On a bright note, brickwork is now the full two storeys high now which is super exciting! Re: Masterton Homes - The next thread 4.0 3097Jan 15, 2015 5:27 pm Good luck Gibson hope its better this time around! Welcome Muzza and Elizabethhills2013. Can't believe they stole from your site R2D2. At least there was no vandalism inside that would mean your build was delayed. So M are back...can't wait to see all the building fun again! Appointments start for us tomorrow! Any last minute tips? Re: Masterton Homes - The next thread 4.0 3098Jan 15, 2015 6:14 pm Mgardz my only tip (from my 75 yr old neighbour) is ... If you really want it, get it. Don't worry about the budget. Whilst an extra $500 here or there seems alot at the moment ... It is the one time in our lives we get to choose this stuff. Don't compromise on the big things (that will be hard to change later on). Not sure if that helps .... 2013 1st tender 24/10 Dep. 18/11 2014 5% 25/02 CDC approval 5/5 Demo 26/5 Pool 3/7 Valid'n 10/7 Slab 11/8 Frame 19/9 Bricks 23/10 2015 Roof 3/12 Lock up 11/2 PCI 31/3 Final insp. & keys 30/4 Re: Masterton Homes - The next thread 4.0 3099Jan 15, 2015 6:27 pm welcome ElizabethHills2013 and Muzza02, MGardz- enjoy your appointment tommorow you are very organised. R2D2 - brickwork nearly done thats great at that rate you might be in mid year KDR. Overture Premier 09/14 $3900 10/14 Plans 11/14 Contracts 03/15 Demo 04/15 Validation 05/15 Slab 06/15 Frame 06/15 Bricks 09/15 lock up 16/12/15 Keys Re: Masterton Homes - The next thread 4.0 3100Jan 16, 2015 12:29 am Hi everyone ,i m new to blog start reading few days ago feels like almost all qustion in mind are alrady answerd.thanks all realy helpfull and informative blog. i m building cello signed contrat and paid 5% on 18th dec.will be submiting external color tomorrow and hopefull process will start . GOOD LUCK every one buliding and congrats to people who already moved in. 4 23457 Hi all Just starting the journey with Masterton and building the Aston Exclusive. Will share the journey in case it's helpful to others. Tender 30 April 2024 Contract… 0 5766 I’ve tried this myself and found that it can really elevate the look of a room, especially when you’re working with timber floors. 1 17338 |