Browse Forums Building A New House Re: Anyone building with Homebuyers Centre in VICTORIA? 1562Jun 20, 2014 9:51 am Site Start 11/3/14 Slab Pour 2/4/14 Framing Complete 8/4/14 Lock Up 1/5/14 Fixing Stage Complete 14/5/14 New Home Presentation 20/6/14 Handover 2/7/14 blog: http://firsthomebuilding.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1563Jun 20, 2014 9:57 am 9/4/14-Site Start 9/5/14-Slab 16/5/14-Frame 21/5/14-Roof 31/5/14-Bricks 6/6/14-Plaster 14/6/14-Fixing 19/7/14 -Flooring 8/8/14 - Keys http://newnestinmelbourne.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1564Jun 20, 2014 10:03 am Site Start 11/3/14 Slab Pour 2/4/14 Framing Complete 8/4/14 Lock Up 1/5/14 Fixing Stage Complete 14/5/14 New Home Presentation 20/6/14 Handover 2/7/14 blog: http://firsthomebuilding.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1565Jun 20, 2014 10:04 am 9/4/14-Site Start 9/5/14-Slab 16/5/14-Frame 21/5/14-Roof 31/5/14-Bricks 6/6/14-Plaster 14/6/14-Fixing 19/7/14 -Flooring 8/8/14 - Keys http://newnestinmelbourne.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1566Jun 20, 2014 10:08 am Site Start 11/3/14 Slab Pour 2/4/14 Framing Complete 8/4/14 Lock Up 1/5/14 Fixing Stage Complete 14/5/14 New Home Presentation 20/6/14 Handover 2/7/14 blog: http://firsthomebuilding.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1568Jun 20, 2014 10:54 am Build Permit-17/12/13 Earthworks-13/1/14 Slab-30/1/14 Frame-10/2/14 Lock Up-7/3/14 Fixing Stage Complete-20/3/14 New Home Presentation-6/5/14 Moved in 17/5/14! Blog: http://dandesbuild.blogspot.com.au Re: Anyone building with Homebuyers Centre in VICTORIA? 1571Jun 20, 2014 11:19 am Site Start 11/3/14 Slab Pour 2/4/14 Framing Complete 8/4/14 Lock Up 1/5/14 Fixing Stage Complete 14/5/14 New Home Presentation 20/6/14 Handover 2/7/14 blog: http://firsthomebuilding.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1575Jun 21, 2014 11:05 am Site Start 11/3/14 Slab Pour 2/4/14 Framing Complete 8/4/14 Lock Up 1/5/14 Fixing Stage Complete 14/5/14 New Home Presentation 20/6/14 Handover 2/7/14 blog: http://firsthomebuilding.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1576Jun 22, 2014 10:25 pm congrats niccles... we went over to our site yesterday...for the very first time, we were actually locked out !! And I think not much work has happened in the past week. This week painting is supposed to start... 9/4/14-Site Start 9/5/14-Slab 16/5/14-Frame 21/5/14-Roof 31/5/14-Bricks 6/6/14-Plaster 14/6/14-Fixing 19/7/14 -Flooring 8/8/14 - Keys http://newnestinmelbourne.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1577Jun 23, 2014 6:02 am Bkoolrocks - we are so close in our construction stages - for the first time yesterday, we were locked out as well. They did some more plaster work this week, put in the kitchen / bathroom cabinetry and installed the solar panels for the hot water system. Painting this week, you say? YAY! 19.03.14 - Land Settlement 15.04.14 - Building Permit 28.04.14 - Earthworks 14.05.14 - Slab Stage 20.05.14 - Frame Stage 11.06.14 - Lock Up Stage 03.07.14 - Fix Stage 15.08.14 - New Home Presentation Re: Anyone building with Homebuyers Centre in VICTORIA? 1578Jun 23, 2014 9:22 am pooks...read through this...something might be common here in regards to ur internet usage... https://www.ozbargain.com.au/node/149830 9/4/14-Site Start 9/5/14-Slab 16/5/14-Frame 21/5/14-Roof 31/5/14-Bricks 6/6/14-Plaster 14/6/14-Fixing 19/7/14 -Flooring 8/8/14 - Keys http://newnestinmelbourne.blogspot.com.au/ Re: Anyone building with Homebuyers Centre in VICTORIA? 1579Jun 23, 2014 11:28 am bkoolrocks pooks...read through this...something might be common here in regards to ur internet usage... https://www.ozbargain.com.au/node/149830 Interesting! Thank you for this. I'm still having huge issues. Only 20gb left out of 200gb 5 days into my cycle Re: Anyone building with Homebuyers Centre in VICTORIA? 1580Jun 23, 2014 11:32 am did u talk to those telstra guys? meantime, im having a chain of emails going on btwn my liaison and she says "Flooring laid" mentioned in Lock up stage is pointing to the concrete floor. I cant understand the logic behind that...without floor, we cant build right...and if concrete floor is mentioned, i guess frames also should be mentioned So as per her argument, my interpretation is wrong and not their contract..and more interestingly I dont see flooring mentioned in completion stage as well...this is fun ! I want them to accept their fault or prove me wrong...till then, im not gonna let go !! 9/4/14-Site Start 9/5/14-Slab 16/5/14-Frame 21/5/14-Roof 31/5/14-Bricks 6/6/14-Plaster 14/6/14-Fixing 19/7/14 -Flooring 8/8/14 - Keys http://newnestinmelbourne.blogspot.com.au/ I havent, and i havent looked to much into it, but on face value its not the saviour its trying to make out to be. Shared equity in your home is never a good idea. The… 1 4122 Hi, have purchased a house with 2 single garage doors. The Centre pillar one side sits proud to the other. Can I change 2 doors into one. Please see picture. 0 6627 For reference, this is the Austlii reference. My take on this is, that they would be breaking the law denying access to a homeowner in Victoria, or their agent from having… 1 9451 |