Browse Forums Building A New House Re: Building in Baldives 8Jun 04, 2015 10:44 am Love your plan! Nice big kitchen and like it how it flows onto the alfresco! Nice block size too... Baldivis quarter is a very nice estate Re: Building in Baldives 10Jun 04, 2015 8:50 pm Nice plan kapes. I love the huge kitchen and dressing room. Are you going to put doors between the dressing room and the ensuite? I just worry about all the steam going onto my clothes, maybe it's just me. Looking forward to following Our building journey viewtopic.php?f=31&t=77582 Re: Building in Baldives 11Jun 11, 2015 4:59 pm Thanks for the comments. Sorry, haven't logged in for a while. Natalie92 - pre-start should be in a couple of weeks. Ourmansion- I like your suggestion about doors between the dressing room and the ensuite. Re: Building in Baldives 12Jun 11, 2015 5:59 pm Love your kitchen! And love your dressing room and ensuite Re: Building in Baldives 13Jun 22, 2015 1:15 am Well, we're having our colour consult on Friday. Have spent most of the last 2 weeks visiting display homes and looking at new home exteriors. Thinking of having ivory gloss tiles for the living/dining/kitchen/passage/activity and jarrah laminate flooring for the bedrooms/theatre/study. White benchtops for kitchen and bathrooms and dark grey cupboards in bathrooms. Light grey cupboards in kitchen. Neutral off-white paint in living areas and light cream in bedrooms/study to complement the jarrah floors. Darker grey paint in theatre Building with Dale Alcock in Baldivis 16Jul 03, 2015 7:39 pm Setting up my timeline
9/05/15 First meeting with Dale Alcock 16/05/15 Offer on Land 4/06/15 Finance for land approved 24/06/15 Building contract signed 26/06/15 Colour consult 29/06/15 Land settled 13/07/15 Building permit received 18/07/15 Pre-start 6/08/15 Finance for construction approved 27/8/15 Moved into construction 7/9/15. Earthworks commenced 10/9/15. Slabbed!!! 25/9/15 Bricks delivered 29/9/15 Bricklaying commenced 5/10/15. Termimesh installed 9/10/15. First on site meet with SS Mark 16/10/15 Plate Height 23/10/15 Roof timber delivered 6/11/15. Roof timbers completed 13/11/15. Eaves completed 20/11/15. Plumbing and I-Homes wiring complete. We have taps!! 27/11/15 Roof and anticon complete. Electrical wiring done. 11/12/15 Grey float complete 18/12/15. White plaster set 24/12/15. Ceilings complete 24/12/15 to 4/1/16 : Christmas break 6/1/16. Cornices complete 12/1/16. Cabinets and shelving 15/1/16. LockUp 20/1/16 On site meeting with SS 27/1/16. Tiling started 5/2/16. Appliances installed 10/2/16. Electricals and plumbing complete 29/2/16. pre-handover 16/3/16. Keys!!! Re: Building in Baldives 18Jul 13, 2015 9:53 pm Hi Kapes, We're also building with Dales, a little further north than you in the Village at Wellard. Hooray for pre-start! What changes are you thinking of making? How are you going with your colours and things? Our Custom Dale Alcock build in the Village at Wellard https://forum.homeone.com.au/viewtopic.php?f=31&t=78620 Re: Building in Baldives 19Jul 13, 2015 9:56 pm Congrats on your land being settled! How did you go at your colour consult? Hope it went well How exciting for Saturday, can't wait to see your selections Re: Building in Baldives 20Jul 16, 2015 12:24 am Hi Wellard2ndTimers and jellbell55. Thanks for your comments. Yes, it is exciting going in for the pre-start. Hope I don't blow the budget!!! Will have to prioritise the wish-list!! Will post the selections once it is over. go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 111062 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 11226 |