Browse Forums Building A New House Re: Coral Homes general build thread 4381Jun 03, 2016 4:33 pm vonsta76 Oh yep thanks for that lexie. Probably need to allow 2 weeks it seems, but its not as if coral follow the same schedule for everyone lol Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 Nope it's a moving and variable target lol Re: Coral Homes general build thread 4382Jun 03, 2016 5:13 pm vonsta76 For those who have been rendered already, approximately how long do they render after bricking? I just got my third progress claim invoice Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 Hi vonsta We have just been rendered and we have already paid bricks and fixings invoice. Inly one more invoice to go for us. Wet areas are tiled, cabinets are in, painting to start mid next week. https://forum.homeone.com.au/viewtopic.php?f=31&t=80908 Re: Coral Homes general build thread 4383Jun 03, 2016 6:32 pm Hi everyone! Has anyone had double height bricks installed by coral ? Re: Coral Homes general build thread 4384Jun 03, 2016 8:16 pm powerfamilybuild vonsta76 For those who have been rendered already, approximately how long do they render after bricking? I just got my third progress claim invoice Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 Hi vonsta We have just been rendered and we have already paid bricks and fixings invoice. Inly one more invoice to go for us. Wet areas are tiled, cabinets are in, painting to start mid next week. Oooh wow painting already?! Thats fast Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 Re: Coral Homes general build thread 4385Jun 03, 2016 8:25 pm vonsta76 powerfamilybuild vonsta76 For those who have been rendered already, approximately how long do they render after bricking? I just got my third progress claim invoice Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 Hi vonsta We have just been rendered and we have already paid bricks and fixings invoice. Inly one more invoice to go for us. Wet areas are tiled, cabinets are in, painting to start mid next week. Oooh wow painting already?! Thats fast Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 Our start date was 12th Jan but Jan and start of Feb were gone due to weather. Slab was 18th March. So we are currently 11 weeks from slab. Hoping to be in mid July https://forum.homeone.com.au/viewtopic.php?f=31&t=80908 Re: Coral Homes general build thread 4386Jun 03, 2016 10:34 pm vonsta76 Oh wow it sounds like you're about 3/4 of the way there. Fingers crossed the train stays on the track for the rest of the build! Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 After 8 months, I seriously hope I don't have another 1/4 timeframe to go... Re: Coral Homes general build thread 4387Jun 04, 2016 7:44 am ASH Jordan Springs vonsta76 Oh wow it sounds like you're about 3/4 of the way there. Fingers crossed the train stays on the track for the rest of the build! Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 After 8 months, I seriously hope I don't have another 1/4 timeframe to go... Oh no sorry I was meaning a quarter left of the build, not timewise. Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 Coral Homes general build thread 4388Jun 05, 2016 12:44 pm This is the issue holding up the build. The crack in the ceiling keeps spreading they still can't figure out what is causing it Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Re: Coral Homes general build thread 4389Jun 05, 2016 12:45 pm [quote="Firstbuild92"]So some work has been done on the house this week. The wooden slats on the portico were put up, benchtops were put on, shower screens and wardrobe doors installed. Appliances are sitting in the shed waiting to be installed! Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Coral Homes general build thread 4390Jun 05, 2016 12:47 pm Love love love it all firstbuild! Gorgeous entry with your niches and so jealous of all these gorgeous porticos with the feature timber panelling! C U S T O M. C O R A L. B R O N T E. 43 http://forum.homeone.com.au/viewtopic.php?t=79581 M Y C U S T O M C O R A L B R O N T E 43 ...............Kitchen! 16 Nov 2016 https://forum.homeone.com.au/viewtopic.php?f=31&t=79581 Re: Coral Homes general build thread 4391Jun 07, 2016 7:36 pm Question - We had our frame invoice sent to us before frames were completed. I contacted CSO who said they would credit that invoice and re-issue when frames were completed and they had received notification from SS. Frames have been finished for over a week now and no new invoice. Anyone had this happen before? I'm concerned frame and exterior invoices are going to come in very close together (banks problem, not mine ). Just curious to know if this has happened to anyone else? Re: Coral Homes general build thread 4392Jun 07, 2016 7:52 pm RugbyElmo Question - We had our frame invoice sent to us before frames were completed. I contacted CSO who said they would credit that invoice and re-issue when frames were completed and they had received notification from SS. Frames have been finished for over a week now and no new invoice. Anyone had this happen before? I'm concerned frame and exterior invoices are going to come in very close together (banks problem, not mine ). Just curious to know if this has happened to anyone else? Yep! That exact same scenario happened to me and it was only because I stupidly alerted them to it that they invoiced me! You won't be penalised as they haven't re-issued the invoice so if it was me, in hindsight, i would be letting it go! C U S T O M. C O R A L. B R O N T E. 43 http://forum.homeone.com.au/viewtopic.php?t=79581 M Y C U S T O M C O R A L B R O N T E 43 ...............Kitchen! 16 Nov 2016 https://forum.homeone.com.au/viewtopic.php?f=31&t=79581 Re: Coral Homes general build thread 4393Jun 08, 2016 6:06 pm Getting so frustrated. Found out our plans were approved by council almost 2 weeks ago. On Monday after ringing to find out what's going on, I was told out plans were back with Coral certifiers and should have ACC issued that afternoon. 2 more days of phone calls to be left with a message that they have only just received the plans back from council today and will take a few more days for process I g etc. All this is now 1 week after we were meant to have our start date by, and when I ask whether they intend charging us extra, they can't answer!! How long it it take others between getting council approval and a start date? Re: Coral Homes general build thread 4394Jun 08, 2016 6:36 pm The next day for us, Bec's Coral, it was issued for a date 19 days away. I should add that we are paying cash so there is no to and fro to a bank to take up extra time.
Re: Coral Homes general build thread 4395Jun 08, 2016 6:39 pm Wow it was a week for their internal approvals to give the ok for me, after council was approved when i got my start date Avoca 25 in Gainsborough Greens Gold Coast viewtopic.php?f=31&t=81406 Re: Coral Homes general build thread 4396Jun 08, 2016 6:40 pm We were pretty close to it as well Bec! I also just wanted to say to keep your chin up, once you get a start date, the build will begin and this will be a long distant memory! Take it from me who during Head Office stage lodged a formal complaint it got that bad! Now I couldn't be happier or recommend coral enough! Our build has made up for it tenfold! As for paying extra, they should be ok without since it's not your fault. Fingers crossed your start date is issued soon and try not to let it dishearten you. Re: Coral Homes general build thread 4398Jun 08, 2016 8:08 pm That happened to us we were ment to have our final start date a week and a half ago and it's been a week since our start date was lodged we haven't been told if we have to pay or not and if they say we have to I won't I couldn't get in contact with anyone to give them what they needed so it's not our fault Re: Coral Homes general build thread 4399Jun 10, 2016 6:04 pm We got the great news of a start date this afternoon for 30/6, 20 days away. So excited for things to finally get started. Re: Coral Homes general build thread 4400Jun 10, 2016 6:35 pm See, that was nice and quick, Becs Coral. Yay, you're on your way. You should check your detail drawings, it may show downpipe within brick pier. 14 14451 Ask the council if there is a chance of getting build over easement exemption. Sometimes easements are unused and 24cm is not all that much. Good luck. And yes any builder… 2 14738 In Qld it is a requirement that a builder must have a cost breakdown, for building a home to the same specification, with the same inclusions and the same finish. So ask… 1 4801 |