We're building a 'Special Plan' through DAH.
Block is 501m2 and is located in the Northern Suburbs.
Block Purchased October 2011
We first contacted DAH in September 2011.
Contract Signed May 2012
Color Selection June 2012
PreStart July 2012
Slab Poured 27.10.12
Soakwells Delivered 1.11.12
Soakwells installed 7.11.12
Bricks Delivered 9.11.12
Building Started 21.11.12
Plate Height 16.01.13
Roof starts 21.01.13
Roof completed 01.02.13
...whoops forgot these dates
Cornices and Ceilings completed 26.02.13
White Set begins 27.02.13
Lock Up 07.03.13
bit slack on dates ...sorry
Tilers Start 25.03.13
Handover and Moved in approx 07.06.13