Australia's greatest home building and renovation community providing you with access to the popular building forum, planning and budgeting tools, and the premium building directory.
Post subject: Lis’ Santorini – DAH - We've moved in!
Posted: Jul 17, 2010 2:25 pm
Bronze Member
Joined: 22 Jan 2010 Posts: 194 Location: Perth, WA
After months of snooping around other threads on the H1 forum, it’s now time to start my own thread as we’re finally starting our build!
The story so far… After purchasing a block in Helena Valley WA, we signed with DAH to build the Santorini (with some modifications similar to the display version, the Ambrose).
Major changes we made to the standard Santorini: - Flipped the front (switched Master & Office with Garage & Theatre) - Sunken Home Theatre - Added Activity - 31c to Master bedroom and living areas - Added bulkhead over kitchen island - Upstand to kitchen island - CS bench & undermount sink to kitchen - Added overhead cupboards - Stacker doors to Alfresco - Blanco kitchen appliances, pivot doors to showers & inset laundry trough (upgrade package) - Added 3x4 workshop to garage - Extended Alfresco Plus a few other things…
Progress so far is that siteworks have begun this week, and hopefully by this time next week – A SLAB!!!
Looking forward to seeing the actual building stage happening, and sharing the experience with others who only know full well the ups & downs of building.
Milestone Dates: Signed PPA: 31st Jan 2010 Signed Contracts: 22nd April 2010 Pre-start: 23rd April 2010 Signed off Final Plans: 16th June 2010 Council Approval: 1st July 2010 Siteworks Commence: 14th July 2010 Slab: 21st July 2010 Bricks Delivered: 13th August 2010 Bricking Started: 25th August 2010 Roof Carpentry: 7th October 2010 Roof Tiles: 19th October 2010 Plaster Float: 2nd November 2010 Ceiling Started: 9th November 2010 Windows Installed: 19th November 2010 White Set: 22nd November 2010 Lock Up: 27th November 2010 Cabinets Installed: 3rd December 2010 Wall & Floor Tiling: 8th December 2010 Applianced Installed: 22nd December 2010 Garage Poured: 5th January 2011 Front Render Painted: 18th January 2011 Gas & Electrical Finals: 18th January 2011 Key Handover: 17th February 2011
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 17, 2010 2:52 pm
Gold Member
Joined: 16 Mar 2009 Posts: 3452 Location: Sydney
Hi Lis. . .WOW I love your house design. I was in a display home recently where they had that set up with the activity room & other bedrooms in their own zone. . .what a great idea! It would suit both young children & teenagers. Love the size of your ensuite & dressing room, sunken theatre room looks good too. My DH would love that workshop in the garage!
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 17, 2010 3:26 pm
Bronze Member
Joined: 22 Jan 2010 Posts: 194 Location: Perth, WA
Thanks Loretta We're hoping the stay in this house for a fair few years so the room zoning was important for (future) kids
DH insisted he got a good sized workshop as we won't be having a shed in the backyard. Workshop, theatre and alfresco decisions were left to him - had to get his way somewhere
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 17, 2010 8:52 pm
Gold Member
Joined: 12 Dec 2009 Posts: 1054 Location: Perth WA
Aaah, the Santorini/Ambrose. Good choice, and I like the changes you have made! We were very close to building that as we really liked the display, but our building broker said DAH had much slower build times than the builder we chose..... you will see from the timeline in my signature however that you have so far moved a bit quicker than we have during the first phase! I'd be interested to know the (approximate) amount you spent spec'ing up the Santorini if you don't mind sharing it. Oh, and if you could put up a slightly bigger plan so I can see what you've done with it!
Keep the pics coming!
Cheers.
_________________ Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 19, 2010 11:25 pm
Bronze Member
Joined: 22 Jan 2010 Posts: 194 Location: Perth, WA
Thanks for the kind comments sleven. Here's hoping the build gets going soon!
Uploaded a larger plan for you westy - sorry, still a bit of a novice with Photobucket. The plan I uploaded isn't our FINAL plan, but you get the gist of it. The additional changes that come to mind are that we added a door between the kitchen & activity/minor rooms, there's a nib wall in the bathroom between the vanity & shower, and some of the openings have been changes from FHO to DHO. Up-speccing has come in at ~$40K but still comes in less than the display model and has the fancier features we wanted, as well as those that aren't in the Ambrose like workshop and larger alfresco.
Been pretty happy with our progress thus far with DAH. All milestone timelines have been spot on, almost to the day actually! Hope it stays that way
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 20, 2010 1:14 am
Gold Member
Joined: 12 Dec 2009 Posts: 1054 Location: Perth WA
Thanks Lis, now I can have a good squiz... I really do like that workshop, I should have extended our garage that bit further and made it a proper work area, then I wouldn't have to worry about the shed out the back. I have the space on that side of the block too. Hmmmm....
Milestones? What are those??! Our builder certainly doesn't understand the concept!
So is your slab on track for Wednesday?
_________________ Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 20, 2010 8:06 am
Gold Member
Joined: 13 Nov 2009 Posts: 1808 Location: Perth WA
oh Lis - how in earth did I miss your new thread... must've had my head in the gutter...
I looooove the plan and can't wait to see your final one with the changes you've made. What are your selections in terms of colour/materials??
Our pre-start variation was approx $40K so I know what you mean
As to having your slab poured this Wed makes me so jealous - we are so behind with ours it's not funny... I found out that our SS is on holidays - mind you not from my CLO but from a fellow H1-er... grrrrrrrrrrrrr definitely didn't get to a good start with our CLO - she prefers to call rather than email and she's not very personable either – hopefully thing will improve. I do prefer email updates though so I have things in writing... I might ask her to email me from now on and only ring me if something urgent.
Weather is perfect for tomorrow so all the best and hope to see some slab photos Thursday??...
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 20, 2010 10:43 pm
Silver Member
Joined: 11 Oct 2009 Posts: 286 Location: Building in Wattle Grove, WA
Hi Lis
I must have had my head in the gutter too. I missed your thread too!!!
Congratulations. Perfect weather for a slab!!!
Loooove your plan and the changes you made. Your hubby certainly has good reason to be most pleased with his new "man land places". No use giving my hubby a workshop, he wouldn't know what to do in it. Ha ha. But at least it leaves us free of DIY disasters, cause he only attempts to look after the gardening at our house. Then again he is chief diswasher, so he will be ecstatic to see that nice new shiny dishwasher when we finally move in. Ha ha.
You must be close to having your slab poured now. Can't wait to see the piccies.
I have been really bad - I haven't yet posted pics of our place and yet bricking is nearly finished. Hubby has had the camera in his car for his daily block stalks. We have only crosses paths late at night and it's been too late for me to be bothered to jump on the computer. This weekend I promise.
Our prestart was $48K too. It adds up quick doesn't it.
13th Oct - Offer on block 4th Dec - Settlement of block scheduled (delayed due to titles) 22nd Feb - Titles Issued 17th Mar - Land Settlement 17th Mar - Pre-start meeting
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 20, 2010 11:37 pm
Bronze Member
Joined: 22 Jan 2010 Posts: 194 Location: Perth, WA
jbarry wrote:
Your hubby certainly has good reason to be most pleased with his new "man land places".
Hi jbarry! Yes, hubby is quite chuffed with his 'man-spaces'. I too will be happy to send him away to the workshop, or the home theatre when the footy is on so I can close the doors and he can yell at the TV as much as he wants Perhaps should have looked at sound-proofing too
Hope to see your latest pics on your thread soon. This weekend, I"ll be checking
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 22, 2010 9:08 pm
Junior Member
Joined: 20 Mar 2010 Posts: 39
HAHAHA OK I have to make a comment, but does it only look to me like there are two roos on the right in the photo with all the roos, well, um, trying to make another roo????
Post subject: Re: Lis’ Santorini – DAH - And so we begin…
Posted: Jul 22, 2010 10:10 pm
Support Team
Joined: 05 Sep 2009 Posts: 18638 Location: 1acre at Winslow, Victoria
Deryck wrote:
HAHAHA OK I have to make a comment, but does it only look to me like there are two roos on the right in the photo with all the roos, well, um, trying to make another roo????