Australia's home building and renovation community providing you with access to the largest building forum and premium directory of trade professionals.
Been checking out this site for some time, very helpful. Many thanx to all of you for your advice and opinoins to each other.
Building in Rivervale Perth WA. Will post some pics when I work out what I am doin'.
Better use a smilie face , seems to be the go.
_________________ Timeline to Date Aug 08-Land Mar 09-Demolition April 10-Subdivision Sept 10-Handover 1 Feb 11-Slab Sept 11-Handover 2 May 12-Stage 2 Sold
Joined: 11 Oct 2009 Posts: 286 Location: Building in Wattle Grove, WA
Hey Echo
Welcome. I'm fairly new at at this too - but there is a wealth of information on here and some very friendly folk.
What company are you building with? Was there land released in Rivervale, or did you buy a battleaxe and demo?
Best way to post photos is through photobucket.com or another third party site. You upload and store your photos on there and then they provide you the direct links for each photo which you can copy and paste into your post. That's the way I've found that works - but some experts in this might have some further tips for you.
13th Oct - Offer on block 4th Dec - Settlement of block scheduled (delayed due to titles) 22nd Feb - Titles Issued 17th Mar - Land Settlement 17th Mar - Pre-start meeting
If I had know how difficult it is to convert files, post pics, join etc, i may not have bothered. Why didnt anyone warn me. But I am Happy I made the effort now. And I got my photos in some kind of an order for the future.
_________________ Timeline to Date Aug 08-Land Mar 09-Demolition April 10-Subdivision Sept 10-Handover 1 Feb 11-Slab Sept 11-Handover 2 May 12-Stage 2 Sold
_________________ Timeline to Date Aug 08-Land Mar 09-Demolition April 10-Subdivision Sept 10-Handover 1 Feb 11-Slab Sept 11-Handover 2 May 12-Stage 2 Sold
Post subject: Re: *Building in Rivervale Pics of Plan etc
Posted: Nov 10, 2009 7:38 pm
Gold Member
Joined: 19 Apr 2009 Posts: 1438 Location: Perth
I really like your floorplan, Echo. And that's the coolest looking slab I think I've ever seen! It seems like such a randomly shaped slab in the photos but makes sense when you see the plans. I LOVE your alfresco area too
_________________ My tac-home-ter: Been in 8 months!
_________________ Timeline to Date Aug 08-Land Mar 09-Demolition April 10-Subdivision Sept 10-Handover 1 Feb 11-Slab Sept 11-Handover 2 May 12-Stage 2 Sold
Post subject: Re: *Building in Rivervale Pics of Plan etc
Posted: Nov 12, 2009 10:14 pm
Gold Member
Joined: 06 Nov 2009 Posts: 1204 Location: Perth
Many thanx to all.
Waiting Waiting Waiting for some bricks and frames and brickies
Has taken a while
We even had pre approval ( which we did ourselves thru council for $50 to make sure we could put the house we wanted on the block before we signed with builder ) 4 monts prior to prestart. Council were clever enough to send approval docs to the property where we wanted to build after they confirmed the demolition of the existing house was to their satisfation. There being no mailbox at that address seemed to elude them. Given that preaaproval already existed there shouldnt have been a problem with any scheduling.
Get this, We have signed 7 revisions of our addendum to date, and this is not counting the 14 variations offered ( 10 of which we went for )
Im not at liberty to say which builder at this time, but do your research if not locked in yet.
Anyone else with any delays they should be expected. I have a few freinds building at the moment and SS's are now required to have a maximum of 21 sites only. There building lul has finished. FHOG has really picked up the pace for building. Sorry to be the bearer of bad news, be thankfull you have a plan in motion. Builders will be busy for the next 18 months at the least while we take advantage of the country's lack of housing.
These are great times we are living.
Wishing all a prosperous future
Christ Im still on my first page and Im ranting. Very addictive this stuff.
Anyone goin for the ducted vacuum package now available, I want one of them ,perhaps in the next house
_________________ Timeline to Date Aug 08-Land Mar 09-Demolition April 10-Subdivision Sept 10-Handover 1 Feb 11-Slab Sept 11-Handover 2 May 12-Stage 2 Sold
Yup. The FHOG certainly did flood the place!! I know that plenty of the smaller sized blocks here in Dalyellup were snapped up quite quickly by the first home buyers looking to build while the grant was still available. And of course they're all getting built/in the process of getting built etc now so it just all adds up.
Have your builders given you a time frame for your build?
Post subject: Re: *Building in Rivervale Pics of Plan etc
Posted: Nov 13, 2009 1:57 pm
Gold Member
Joined: 06 Nov 2009 Posts: 1204 Location: Perth
Jodie, Is scheduled for Monday week to begin bricking
Will wait and see. Busy preping the place we are in now for sale april/may next year. The slab down Friday October 2nd and still no bricks is a tad depressing, however they have put in soakwells ( 2 x massive concrete ones that we could not have installed ( especially the rear one ) without hiring a crane, plus all the pipes running into the soakwells that will match the downpies at a later date, should save us some time when we start finishing the outside of the house.
Not sure how to handle the paving for the driveway yet. Is 120 sqm and nearly 35 meters long to the rear block, builder has thrown in the turning circle etc . Maybe get the same people to do the crossover as well. Plenty of time to think of a solution.
MMMMmmmmmm Solid Karri Floorboards , a fridge that dipenses ice, decked alfresco and my spa. Dreamin'
_________________ Timeline to Date Aug 08-Land Mar 09-Demolition April 10-Subdivision Sept 10-Handover 1 Feb 11-Slab Sept 11-Handover 2 May 12-Stage 2 Sold
Bugger, Got a parapett wall thats gotta be built. Have to remove a section of fence.
_________________ Timeline to Date Aug 08-Land Mar 09-Demolition April 10-Subdivision Sept 10-Handover 1 Feb 11-Slab Sept 11-Handover 2 May 12-Stage 2 Sold
_________________ Timeline to Date Aug 08-Land Mar 09-Demolition April 10-Subdivision Sept 10-Handover 1 Feb 11-Slab Sept 11-Handover 2 May 12-Stage 2 Sold
And builder says external bricks to be delivered when they make some more of em cos they have run out ETA 3 weeks.
Kinda takes the enthusiasm out things.