Browse Forums Building A New House Re: Who is building with Beechwood 101Feb 24, 2011 6:50 pm Thats great news JacknRuby at least you will have something to look at when you visit your block. I cant wait till I am at that stage,even better till its finished! Look forward to pics. Penny Paid deposit-22/3/11 Plans ready and signed off 23/4/11 Plans submitted to Council 23/5/11 Plans received in post 31/5/11 Contracts signed 3/6/11 Ready for slab 8/8/11 Finished and in 19/12/11 Re: Who is building with Beechwood 102Feb 24, 2011 7:39 pm Hi Acrebuild1, Benching is levelling the land, they do this before they start piering and and excavating. Exciting stuff starting to happen at last!. Re: Who is building with Beechwood 103Feb 24, 2011 8:01 pm hmmm well I happy to report that after a visit to the block we have a the temp fence and a porta loo ....but no benching as advised by the CSO, now what to do.....do I say something to Beechwood or not......cause they have been untruthful....but on the otherhand we do have action on site.....decisions.....??? Will take some pics on the weekend!!! Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 104Feb 24, 2011 8:16 pm Oh, i call that siteworks or earthworks. Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 105Feb 24, 2011 9:04 pm Ring Beechwood or email if you have someone you can email. All our stuff was done by email to the site supervisor and a lady in head office so there was a "paper trail". Over 300 emails Have photos but not much different to the other day but will post on weekend. But we are nearly there!!!!! just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Re: Who is building with Beechwood 106Feb 25, 2011 7:39 am Hi, Whilst I havent been to the block...my hubby took a pic for me, and we are very excited. [IMG] Cant believe you can get so excited over a Porta Loo and Fence..... Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 107Feb 25, 2011 7:41 am Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 108Feb 25, 2011 6:57 pm How exciting. so very jealous - hopefully that will be us next wee (although we wont be having temp fencing as our 5acres are fully fenced already) Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 109Feb 25, 2011 7:27 pm Thanks Acre....I am feel for you Further good news they did the benching today so site is now ready for form work and slab! I will post pics later! Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 110Feb 25, 2011 8:40 pm Hi everyone How exciting for JacknRuby, They will be sick of me by the time i finish building I will probably call them every second day! I would be excited to see fencing and port a loo as well. I thought they signed a 19 week contract is that the case for everyone? or is there something in the contract that they can use to not stick to the 19 weeks? The way they explained it to me is that the 120 day tender is for drawing plans and Council. The the 19 weeks is for the building. One can live in hope i guess. Has anyone built the Genesis series yet ? i am wondering what the tiles are like? Paid deposit-22/3/11 Plans ready and signed off 23/4/11 Plans submitted to Council 23/5/11 Plans received in post 31/5/11 Contracts signed 3/6/11 Ready for slab 8/8/11 Finished and in 19/12/11 Re: Who is building with Beechwood 111Feb 25, 2011 9:33 pm Penny - our build contract is 23 weeks....I too thought 19 weeks but nope and they would budge on it either, we tried for 19. I have uploaded the Genesis tiles (well a few of them anyway), ask me I might just have a pic, I take pics of everything....LOL, otherwise I get home and forget and imagine something else.... Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Have to say the selection wasnt too bad....we choose a pretty neutral tile beige, we went to Westside Ceramics in Lansvale I am not sure if you guys have to come there to select, they are pretty good and have a big range to choose, but you do spend more there too.....we picked a feature tile for the bathrooms extra $125 each bathroom. Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 112Feb 25, 2011 9:45 pm Penny sorry hit the post button before I finished..... Just a note with the 120 days tender, we actually got caught out as intitally our land wasnt registered when they prepared the tender therefore couldnt submit to council till regisitration of the land which was 4 months after the last tender, so we got caught with a price rise which was $3k more.....and almost got caught with another one as there was another price rise on the 1/1/11 on the base prices as then had issues in council (nothing to do with beechwood but they dont hurry the council either)so it was in council for 10 weeks instead of the usual 4-6weeks. Our council has online tracking so maybe yours does too and i just logged in each day and watched our application, this how I found out we had an issues so I then called Beechwood to get resolved. Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 113Feb 28, 2011 9:09 am Hi all We have good news too! We received the commencement letter from our bank on Friday (only took 1 week to get the letter!! yay!), so looks like we'll have some action on our block in the next few weeks! Can't wait for the day we visit our block and see something has happended- so exciting!!!! The Asquith (modified) Deposit:6/2010 Council:12/2010 Contract Signed:15/2/2011 Site Prep:17/3 Slab:11/5 Frame:23/5 Bricks:11/7 Roof:18/7 Gyprock:3/8 Kitchen:6/8 Painting:10/10 KEYS!!: 10/11/11 Re: Who is building with Beechwood 114Feb 28, 2011 7:01 pm Thats great news Melc500 How exciting it will be your turn soon to post pics! Thanks JacknRuby for the pics and advice. Hope to see pics of your slab finished real soon. Hope your husband finds the Merlot directions ok and hopefully no one is living in it yet so he can peek inside! My Tender is in the post and i hope to go pay deposit in a couple of weeks. Penny Paid deposit-22/3/11 Plans ready and signed off 23/4/11 Plans submitted to Council 23/5/11 Plans received in post 31/5/11 Contracts signed 3/6/11 Ready for slab 8/8/11 Finished and in 19/12/11 Re: Who is building with Beechwood 115Feb 28, 2011 7:18 pm Some news for us - FINALLY our file went to the construction department today and im to call them on Wednesday with a start date. Does anyone know how long this normally takes, the 28 days is up TODAY so they were meant to have started today. They got the letter to commence onthe 1st february so my patience is starting to wear very THIN. Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 116Feb 28, 2011 8:36 pm Melc - Yey for you, let hopes it all quick from here in.... Acre - Thats kinda of good news for you, Our when to construction 2 days after receiving our letter and that was on the 9/2 and they have just got on site last week, benching done now, now just waiting for confirmation of when piers will be done, but its raining here in Sydney so god only knows....I am praying the rain will stop! wouldn't they now in breech of the contract? hmmm what to do.....just keep calling or emailing them everyday. I bet your patiences are just about done, mine certainly would be.....Good Luck.. Dont worry I have 150 Tonnes of dirt to get rid of, after them saying it would be 35tonnes......looks like a expensive little exercise like $4-5k... Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 117Feb 28, 2011 9:25 pm Hello, I'm new to this site and new to the building process! We're building the Cremorne in McKeachie's Run, Aberglasslyn. Has anyone built this house? I'd be interested to see other peoples modifications... Cheers, Sarah McKeachies Run, Aberglasslyn Deposit paid 11th April Land registered 6th June Land settled 20th June Colour selections and contract signed 5th August Commencement letter received 26th September Re: Who is building with Beechwood 118Mar 01, 2011 10:06 am jacknruby Melc - Yey for you, let hopes it all quick from here in.... Acre - Thats kinda of good news for you, Our when to construction 2 days after receiving our letter and that was on the 9/2 and they have just got on site last week, benching done now, now just waiting for confirmation of when piers will be done, but its raining here in Sydney so god only knows....I am praying the rain will stop! wouldn't they now in breech of the contract? hmmm what to do.....just keep calling or emailing them everyday. I bet your patiences are just about done, mine certainly would be.....Good Luck.. Dont worry I have 150 Tonnes of dirt to get rid of, after them saying it would be 35tonnes......looks like a expensive little exercise like $4-5k... jacknruby put a sign on it free fill and see if you get anyone to come and get it.....you will be amazed to see how many people will want it Amanda you know the trouble I had with everything in this build....hold them to the 23 weeks contract ours has been over 8 months now....but the finished product is good. Should be finished next week...now the bank is holding back the last payment until the insurance is done.....and the bank is doing the insurance.....catch 22 just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Re: Who is building with Beechwood 119Mar 01, 2011 10:38 am SarBear, welcome - we are renting just nr mckeachies whilst we are building I phone them today and the construction dept hadnt received my file but were today! they said i need to call Steve who does the slabs next week with a program (ill be doing in thursday) Im think im past being patient - its been next week, na, another week, within a fortnight, give it another week, we are a staff member down, please bare with us - it will be atleast another week ...gggrrrrrr Also those who are not getting the phone connected, Do you still have to organise to have the cables laid? Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 120Mar 01, 2011 10:51 am We haven't got a home phone so we didn't get the cables laid. We were going to but they dug and laid the electricity cable in about 4 hours and didn't tell us what day they were going to do it. So we have no home phone or even the cables to connect the phone. If you want it done you need to organise for a telstra contractor to come and connect while the trench is open.....good luck with that. just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ I’m curious about how you went with this. We are planning a KDRB and considering Plantation Homes as a builder. I’m aware that after the demolition another soil test… 1 6315 i wouldn't be worried, you'll definitely miss something, no matter how many times you review. we've spent close to 5 months ensuring everything got reflected in the… 5 9437 Thanks for your reply. I will just wait and see I guess. Trying to get some more information from our builder. 9 11711 |