Browse Forums Building A New House Re: DA vs CDC (Approval Times) in Ku-ring-gai Council? 2Feb 13, 2024 4:38 pm minho Hi all, Anyone have experience/knowledge on how long usually either the DA or CDC process it takes for building a new home in the Ku-ring-gai Council area? (Area's such as St Ives, Pymble, Gordon, Kilara)? Thanks in Advance Hi Minho I have heaps of experience in Ku-ring-gai with both DAs and CDC ( this is the main area we build in). DA's are taking 12-18months and CDC's we have been doing in 2-3 months. If you can get your approval via CDC I would highly recommend it. Council is incredibly slow, pedantic and their approval conditions are onerous. All the best Simeon Architectural Homes & Duplexes - specialising in custom designing homes to your budget Get a Free Onsite Consultation Today or send a PM for information, questions or advice. hey nedket, We have a similar lot like yours . just wondering how is it going with your DA application, is the Blue line is the correct solution (offset the rear boundary… 1 9457 I want to build a bigger driveway (without a nature strip) than has been approved under my CDC. I’ve also had a DA approved to build a deck. It looks like I can do this… 0 5001 CDC Housing Code 3 When to apply Floor Area external face of wall vs Gross Floor Area internal face of wall. Reading thru CDC Housing Code 3, lets take a lot 915sqm.… 0 17221 |