Had tile meeting today - a few little issues but hopefully they will be resolved.
Also managed to put the ss on the spot for our timeline - 10 weeks til completion. I cant see why it will take so long as we are doing alot of things after handover. Here's my to do list (I hope you don't mind burns I copied yours and edited it)
Tiling - commenced
Completion of painting
Termite treatment No 2 - not sure but think this may have been done already.
Electrics and rangehood
Door Furniture
Tapware install
Roof Batts
Garage door - already measured
Shower screens & mirrors
Towel rails
Flyscreens
Final Clean
Practical Completion