Browse Forums Building A New House Re: Building with Rendition in Lockleys 14Feb 28, 2017 3:53 pm Hi Is it single story or double story? In the contract it had the maximum amount of time allowed and ours was 34 weeks and they were just inside that. We had Xmas in that time so that's 2 weeks gone. I think lock-up is about half way. Of course that depends on what the builder is doing at the end of your job. We did our own floors, driveway, landscaping, stormwater...so that saved some time. We have been in for a year and the house is great. I much prefer a builder who takes his time and gets it right the first time. I have heard some horror stories from rushed jobs and had a few friends with major problems that thye only found after handover. Hope this helps. Slab: 14/5/15 Frame: 01/07/2015 Roof: Upper floor 01/08/2015, lower floor 28/09/2015 Lock Up: 30/10/2015 1st Fix: 06/11/2015 PCI: Handover: Hey guys building a new place through a volume builder and just wondering if i should complain to the site supervisor as we just had plasterboard installed. Looks like… 0 11845 Elvis has left the building... The site supervisor quit after 2 month on the project. I guess he was just instructed to bark at people, but didn't like when he was… 26 21641 |